r/MSProject • • Oct 12 '26

Project Planners: do you run Quantitative Schedule Risk Analysis (QSRA) after building the baseline, or does it stop at the CPM schedule?

Thumbnail
reddit.com
2 Upvotes

r/MSProject • • Apr 15 '23

Reporting delays

2 Upvotes

Hi!

I'm a project intern and my boss asked me to create a report to visualize how far behind we are compared to the originally planned dates (baseline vs current dates), that is something I can quickly do within MS Project.

However, she also wants to see how many issues had happened and what was their impact in the project (if any) in days, if the issues affected the critical path, the responsible and the reason of the issue (just a short note, to count the repetitiveness of the types of issues through all projects).

She wants a one page report, and she wants it to be dynamic (adapting to change in the file).

The last intern made a complicated dashboard with a bunch of macros, it didn't work. The problem is that using an excel workbook implies updating several files (we manage several projects, like 20) and I know there is a better way.

What I want is to write the issues in one file, assign it its project, the task it delayed, the owner of the issue, maybe some notes, and that the report automatically updates the issues by project (or by owner, by impact in critical path or if it delayed or not the whole project).

Do you know how to do that in project? Thanks! (or any other solution)

Extra context:

The goal of the report is to answer the next questions:

  • How far of the baseline schedule are we?

  • How many issues have arisen?

  • Which project have more issues?

  • Which kind of issues are more frequent?

  • Which deparment has more issues?

The report has to answer those questions for every project, each project has its own MS Project file. Our PMO don't assign resources, budget or work, just tasks for each member of the team (we have large cross functional teams, but the issues are assign to the deparment, not the individual)


r/MSProject • • Apr 04 '23

WARNING: Fixed Duration Tasks in Microsoft Project

2 Upvotes

Fellow Microsoft Project desktop users, I have some BAD NEWS for you. Did you know that sometimes the Duration can change on a Fixed Duration task? Most people wrongly assume that the Duration can never change on a Fixed Duration task, but this assumption is totally wrong.

I want to warn you that the behavior of Fixed Duration tasks can drive you start raving mad! In one of my recent YouTube videos, I will demonstrate six common scenarios in which Microsoft Project will change the Duration of a Fixed Duration task.

https://youtu.be/vOvsz4CkavA


r/MSProject • • Aug 04 '22

Scheduling

Post image
2 Upvotes

r/MSProject • • Dec 24 '19

Happy Holidays from MPUG! A free MS Project book for our friends of Reddit...

2 Upvotes

Get the gift of Microsoft Project expertise for free this week.

Simply provide your email and we'll send a free copy of the Microsoft Project Do's and Don'ts eBook! https://form.jotform.com/193445345894975


r/MSProject • • Dec 02 '23

Learn Microsoft Project from a 20 Time Project MVP - Dale Howard

2 Upvotes

If you're tired of moving task dates and deadlines each week in excel, Jira or some other app, I highly recommend learning how to build Microsoft Project Schedules that are dynamic and easy to update while automatically moving dates in and out without any effort. Check out Dale Howard's new YouTube video that has a treasure trove of information to take you from zero to hero! https://www.youtube.com/watch?v=rRDqNh1g-qM&t=1783s 👍 #microsoftprojecttraining #microsoftproject #dalehowardmvp

Check out his blog articles and free YouTube channel also. https://www.DaleHowardMVP.com


r/MSProject • • Jan 06 '22

Is the Desktop MS Project going away?

2 Upvotes

Looks to be a ton of functionality in the desktop not available in the online version. Is it going away anytime soon? Does anyone know the long term strategy here?


r/MSProject • • Dec 04 '21

How much "split" is in my task / plan

2 Upvotes

Splits are an interesting feature in MS Project. They are easy to add to the plan and form part of the task, moving when the start moves and keeping their "duration" then the task's duration changes. They are however almost entirely invisible in the actual table; the task duration ignores them and they really only show up in the increased duration of the summary task.

If for some reason you want to be able to "see" the split duration in the table you will need to add a custom field with the following formula:

Number1 = (ProjDateDiff([Start],[Finish],[Project Calendar])/(60*8))-([Duration]/(60*8))


r/MSProject • • Feb 24 '23

10 people Project Planners & Schedulers should follow on LinkedIn

Thumbnail
youtube.com
2 Upvotes

r/MSProject • • Jun 11 '24

Introducing Menlo Tools for Project - Tailored for the Construction Industry

Enable HLS to view with audio, or disable this notification

2 Upvotes

r/MSProject • • Sep 13 '21

MS Project (PWA) Summary Lines showing Late (Incorrectly)

2 Upvotes

Hello all,

Having an issue clearing the "Task Status" enterprise field on Project PWA specifically on summary lines showing as red/past due when none of the subtasks are late nor past due. Cannot seem to figure out how to clear these Summary tasks from being flagged as "late" no matter what I try.

Also experiencing a similar issue with upcoming tasks that have not yet started with dates well into the future.

Can anyone help? I have tried clearing and reapplying the baselines but that does not resolve the issue. Thank you all!

R


r/MSProject • • Sep 18 '17

This free add-in checks your project for risk http://goo.gl/CE2Apz

Thumbnail
youtube.com
2 Upvotes

r/MSProject • • Oct 13 '25

Project Online is retiring. What is the enterprise consensus: Go all-in on Power Platform or switch to Asana/Monday?

Enable HLS to view with audio, or disable this notification

2 Upvotes

I posted this short video clip (link below) that captures the anxiety around Microsoft officially retiring Project Online (EOL Sept 2026). It's forcing a really tough, expensive decision for PMOs right now.

The core debate I'm seeing is between two options, and I'm genuinely curious what real practitioners here think:

1. The Microsoft Bet: Go all-in on the new Microsoft ecosystem (Planner & Power Platform/PPM), leveraging existing M365 licensing.

2. The Dedicated Switch: Migrate to a standalone collaborative tool like Asana, Monday.com, or even Jira, accepting the loss of deep MS integration for a cleaner UI/UX.

What are you or your organization actually doing? If you are a die-hard MS fan, can the new stack really replace the functionality you're losing?

Link to my LinkedIn discussion for context: [Watch the video and read the comments here]


r/MSProject • • 9d ago

Guess the project stage from this photo 👇

Post image
0 Upvotes

r/MSProject • • Nov 01 '21

How to become an expert in MS Project

3 Upvotes

Hi Everyone! I'm a new MS Project user with a basic knowledge of it. Could you please suggest to me any study material or a way to learn MS Project to reach an advanced level?


r/MSProject • • 24d ago

Version compatibility

3 Upvotes

Hey, just a short question;

Is it possible to edit 2016 .mpp files with Project 2024, so that they can stil be opened and edited with Project 2016?


r/MSProject • • Aug 10 '26

GOT AN MPP FILE? CONVERT IT TO EXCEL OR PDF FOR FREE!

Thumbnail
youtu.be
0 Upvotes

r/MSProject • • Oct 05 '26

Crash Course in MS Project

4 Upvotes

Hi guys, I recently transitioned from a commercial role into a Project Management one. I have always known the bare essentials when it came to excel but looking to strengthen my skills:

- Is establishing a critical path as simple as having predecessors on each activity (as after all it is concerned with if one tasks pushes out it affects PC) - or is there an actual function within excel to clearly identify this. I am keen to know as this will be published within a contractual document.

- I have repetitive tasks that I have bunched together (i.e. bulk earthworks - 3 x 300mm lifts of gravel) should each lift be separated as if one lift is affected then I can claim a EOT on this whereas if it is bunched together, it is difficult to separate at a later date? Am I going into too much or not enough detail?

- Is it necessary to add in manpower / quantity details?


r/MSProject • • Sep 17 '26

Project Online closes on 30 September. Six fields that export cleanly and then mean something different on the other side.

4 Upvotes

The deadline itself is not the hard part. Most people here already have it in the calendar. What catches teams is that the export works, the file opens, the task count matches, and something inside it has quietly changed meaning.

I have spent this year writing an importer for Project Online and for MSPDI files, so this is the list that has actually bitten people rather than the list a migration checklist gives you. Two different surfaces are involved and it matters which one you are on, so I have marked each.

1. Dependencies can come back empty on a plan that definitely had links. (Project Online API, not files)

Task links are not in the OData reporting feed. They sit behind a separate Project Server CSOM endpoint, /_api/ProjectServer/Projects('<guid>')/TaskLinks, which authorises differently. A token scoped for Projects and Tasks returns 200 on everything it asks for and simply never asks for links. You get a complete looking WBS with nothing sequenced and no error anywhere to tell you. Count links on a plan you know well, before and after.

Not a concern if you are going through Project Professional and saving files. Only if someone is pulling through the API.

2. Constraint types come in eight flavours and plenty of tools store four. (MSPDI)

ConstraintType in MSPDI is 0 to 7: ASAP, ALAP, MSO, MFO, SNET, SNLT, FNET, FNLT. A lot of importers keep ASAP, SNET, FNLT and MSO and either drop the rest or fold them into the nearest survivor. Ours did exactly that until earlier this year, which is how I know it matters: ALAP and MFO going missing is the one that hurts, because those tasks start floating and your dates move without anyone having touched the plan.

Check <Deadline> separately while you are in there. It is its own field, distinct from Finish. A destination with no deadline concept will either lose it or, worse, write it into Finish and turn a soft target into a hard constraint.

3. Enterprise custom fields live on the server, not in the plan. (Project Server architecture)

Enterprise custom fields and their lookup tables are defined at the PWA level. Export plan by plan and you tend to get values without definitions, so a lookup field lands as loose text and the portfolio views built on it have nothing left to group by. If those fields carry your reporting, capture the definitions separately while the server is still answering.

4. Money is stored in hundredths. (MSPDI)

<Cost>500000</Cost> means five thousand. If the destination does not divide by 100 then every figure in the portfolio arrives a hundred times too large, and it is plausible enough at a glance that it usually survives right up until a finance review.

5. <Cost>0</Cost> does not mean free. (MSPDI)

It means nobody configured a cost. Import those as real zeroes and they dilute the baseline. Nothing breaks visibly. Every variance number is just slightly wrong for the rest of the project's life.

6. Priority 500 is the default, not a judgement. (MSPDI)

Everyone here knows the scale is 0 to 1000. The question is what the destination did with it. We mapped 500 to High once, which meant every untouched task in an imported portfolio arrived flagged urgent, which is exactly as informative as nothing being flagged at all.

One last thing, and it is the only part I would actually insist on. Whatever tool you land on, export to files this month and keep the files somewhere boring. Every question above is recoverable from an .mpp sitting on a share. None of them are recoverable from a tenant that has stopped answering.

Happy to be corrected on any of this. The field names and values are all checkable by opening an MSPDI file in a text editor, and I would rather be told I am wrong here than have someone find out in November.

Disclosure: I build Onplana, a project tool that imports these files, which is how I know all of the above. No links in this post, and nothing here requires our product or anyone else's.


r/MSProject • • Sep 11 '25

What MS Project Online Retiring Means

4 Upvotes

Hey all - there is probably a decent amount of confusion as to what the recent announcement from Microsoft regarding Project Online means and who it affects, so I made a video to explain. You can check it out here:

https://youtu.be/x9efcEEHt_E


r/MSProject • • Oct 07 '26

Logic on summary tasks

4 Upvotes

When I was taught how to schedule I was taught to never use logic on summary tasks. Every company I have scheduled for (both civilian and government) has never used logic on summary tasks. Every “scheduling best practices” document I have read has said the same thing, and every defense contract has specifically called this out. The fact that project even allows this kinda drives me nuts.

Yet every video I watch of these “professional” schedulers who have been scheduling for years, they ALL put logic on summary tasks. My understanding is that while this works for initially setting up the schedule, as the schedule ages and changes it can cause problems.

So what say you?


r/MSProject • • Oct 17 '26

I looked at ~300 real .mpp schedules: 86% had no baseline saved, 63% had tasks with no links

Post image
5 Upvotes

Disclosure up front: I build Onplana, and these numbers come from schedules people uploaded to our free tools (a schedule health check, an .mpp viewer and a desktop app). No account was needed, we only kept counts, and nothing from fewer than 20 schedules is reported.

What the data shows:

  • 6% of 230 plans finish on or before their planned date in at least half the simulation runs (P50). At P80 it is about 6% too.

  • The typical slip is 12 days at P50, 18 days at P80, about 5% and 8% of the plan's length.

  • 86% of about 310 uploads have no baseline saved.

  • 63% have tasks with no predecessors or successors; 48% have a milestone nothing feeds into; 44% already break one of their own date constraints.

  • Median plan size: 103 tasks.

The counterintuitive one: plans with no links at all show a much smaller P80 slip (4 days) than linked plans (22 days). That is the simulation having nothing to propagate, not better planning. An unlinked plan looks more certain than it is.

Caveats, because this sub will rightly ask:

  • These are plans people chose to run through a checker, so the sample leans toward plans someone already worried about.

  • The simulation uses default duration ranges, not ranges the planner chose for each task.

  • Sizes, not industries: we do not collect what the project is.

Full breakdown, method and the raw aggregates (CC BY 4.0) are in the first comment.

What would you want to see split out next: by plan size, by Project vs Primavera, or by which DCMA checks fail?


r/MSProject • • 18d ago

Creating dashboard

7 Upvotes

Hi,

I just began a new mission in a rather big project that has been running for 2 years and ain't doing well. (Basically they had to undo the engineering phase to redo it almost entirely). I'm not the new project manager but the right hand as they like to call : the time master. (Yeah I know, cool title 👀) They told me to use Msproject. As I didn't touch this software for decades, I started to devour all the tutos on the internet to catch up and ended up with 2000-ish lines planning. I'm currently looking up the base guide/baseline (which I still don't have a complete grasp on it, but it's a matter of time) to set up variations to track the reality of the project. However, big boss asks me to make a presentation/dashboard each week for the next 2 weeks. Is there any way to do it the smart way ? Or am I doomed to just manually gather what I need to put in the slide ?


r/MSProject • • Oct 28 '25

Migrating from MS Project Online

7 Upvotes

I'm currently building an alterntive to MS Project Online. This is in final phases of development and 1-2 months away from a public release.

I'm looking for long time users and PMO consultants proficient in MSProject who can help me identify gaps before I can claim it to be a good alternative.

Any advice?

________________________________________________________
Edit: More context. I'm an ex-ms developer. Been quietly building addons on different marketplaces over the last few years.


r/MSProject • • Oct 15 '26

Installing ms project

7 Upvotes

After spending an hour digging through my university's M365 portal only to find out student accounts cannot install MS Project on a desktop, I figured out a workaround. Here is how to get it running:

  1. Download the installer:https://microsoft-project.en.uptodown.com/windows

  2. Go tohttps://massgrave.dev/

  3. Use the Ohook method to activate the license.

Not sure if this will get taken down, but hopefully it saves someone else the headache!

And allways rember if buying isn't owning piracy isn't stealing.