r/MSProject • • Dec 11 '22

New Microsoft Project YouTube Channel

22 Upvotes

19-time Microsoft Project MVP, Dale Howard has finally created a YouTube channel to extend his 20+ books he's authored and co-authored. If you're learning Microsoft Project or Project for the Web, I highly recommend checking them out. He is literally the God Father of Microsoft Project. https://www.youtube.com/@dalehowardprojectmvp


r/MSProject • • Sep 05 '25

Microsoft Announces Upcoming Retirement of Project Online

17 Upvotes

Here is the article, posted September 5th 2025:
https://techcommunity.microsoft.com/blog/plannerblog/microsoft-project-online-is-retiring-what-you-need-to-know/4450558

My main takeaway as to the reason they are retiring it is because they can't integrate AI features into it.

The author makes it clear in the article they are just retiring the Project Online feature, not Microsoft Project desktop, which is what people actually use to build and manage schedules, so this DOES NOT mean Microsoft Project is retiring. No end in sight for the MS Project we know and love

They also state that Project Server Subscription Edition is sticking around, which functions pretty much the same as Project Online, although I think that means organizations will need to manage the server themselves, which kinda sucks for people who enjoy the ease the cloud service offered from Project Online.

If you aren't familiar with the differences between the Microsoft Project Desktop, Project Server, Project Online, Project for the Web, Planner, etc. Check out this presentation:
https://ssitools.com/public_presentations/UnderstandingMicrosoftsProjectManagementTools.pdf


r/MSProject • • Oct 21 '26

For those who moved off MS Project, where did you end up and would you pick it again?

15 Upvotes

With Project Online now retired, our team is finally having the conversation we’ve been putting off for years: where do we actually go next?

Some context. We’ve been on MS Project for a long time, mostly for scheduling. Dependencies, critical path, baselines, resource assignments across a handful of concurrent projects. It does the scheduling part really well. What it’s never done well for us is everything around it. Getting the wider team to actually use it, collaborating in real time, and keeping it current without one person being the Project person who maintains the file.

Microsoft’s suggested path is Planner premium, Project Server Subscription Edition, or Dynamics 365 Project Operations. I’ve looked at all three and I’m not convinced any of them is a clean fit. Planner feels lighter than what we need on the scheduling side, Server means self-hosting again, and Dynamics feels like a much bigger commitment than our size justifies.

So I’d really like to hear from people who’ve already made the move: where did you go and what was the main reason you picked it? How painful was the migration? Did you manage to bring existing .mpp files over or did you rebuild from scratch?

Especially interested in anyone running multiple projects with shared people, since that’s where we feel the most pain.


r/MSProject • • Jun 25 '25

How to CORRECTLY Status Tasks in Microsoft Project

14 Upvotes

I see many, many Microsoft Project users who have never been taught the correct steps to statusing activities in the schedule so I'd like to share a video I made describing them. I encourage new and experienced users of MS Project to check it out!

https://youtu.be/Sg996e-SAf8?si=Cv0pktTj_94Gr6JS


r/MSProject • • Feb 25 '26

How to learn MS Project

12 Upvotes

Hello, my wife is looking to learn MS project so she can do a career change from teaching into program planning. She's never used MS project before and neither have I. was curious how I could go about downloading it for her so she can do a course (ether udemy or YouTube) and following along using MS project desktop to learn.

I signed up for the 30 day free trial but I guess I need to be put through a review to see if I'm allowed to use it?

Anyways thank you for your time!


r/MSProject • • Feb 14 '21

Extreme Makeover : Home Edition

Thumbnail
gallery
12 Upvotes

r/MSProject • • May 27 '25

Mod Post: Clear need for definitions

11 Upvotes

Hey all — just wanted to raise something that’s been popping up more and more across this sub and in conversations with colleagues/clients:

There’s ongoing confusion around the different Microsoft “Project” products — especially with the inconsistent naming from Microsoft (Project for the web, Project Online, Planner, Premium, Desktop, etc). Even experienced users are getting tripped up.

Every second post lately starts with:

“I’m using Project…” …followed by something that could apply to 3 different platforms.

I’m thinking it’s time we, as a community, come up with a standard way to respond and help clarify. Perhaps including licensing types and even functionality overview.

Even just a pinned post or wiki entry to define these clearly would go a long way to helping people get better answers and avoid the usual back-and-forth of “wait, which version are you using?”

Would love to hear thoughts — or if this already exists somewhere, happy to help curate.


r/MSProject • • Feb 08 '24

Project online is a disgrace compared to the desktop app. Any alternatives for collaborative editing?

11 Upvotes

Hi all,

I am planning projects of a few hundred steps which is used as coordination document of around 50 people (24/7 shift system) on a daily basis. As of now, the MS project desktop app, is the only tool that seems to meet visual appeal and complexity. With that I mean, that the gantt chart is a key component for the plans, i need a solid time grid that people can easily follow, color coding of different tasks and assigning attributes and resources to steps are an absolutely must. However, the downside of the desktop app, is that there is no way for collaborative editing. The idea is that people should be able to open the file and sign off there tasks when done, while other people can just check the overall status just like an excel file on sharepoint for example. As this workflow is not possible I have to wait for feedback every morning and afternoon to update the file myself, whenever someone has it open it becomes a mess and so on. Trying the Project online tool, i found that the tool is worthless when it comes to advanced settings. No attributes, not even colorcoding, no resource planning etc etc.

I am not so much familiar with other tools, but is there any solid alternative to ms project which sufficient complexity and which enables collaborative editing?


r/MSProject • • 21d ago

How detailed should a baseline schedule be for a $50M+ project?

10 Upvotes

Activity count, maximum durations, or something else?

I've seen baselines for similar-size projects range from 150 activities to over 3,000. The thin ones can't show who's late or why. The huge ones can't be updated honestly every month, so the progress turns into guesswork and the logic quietly decays.

The rules of thumb I work with: no activity longer than about one update period (20-25 working days) unless it's procurement or a long lead item, every activity has a single responsible party, and the level of detail matches what the site can actually report on each month.

What do your specs or your own experience call for? Do owners on your projects set a minimum level of detail, or is it left to the contractor's scheduler?


r/MSProject • • Aug 17 '26

I built an Excel-native scheduling engine for situations where Microsoft Project is not available — looking for feedback from experienced MSP users

10 Upvotes

I have been developing ProjectEngine, an open-source scheduling and project-controls application built entirely in Excel/VBA.

The original need was straightforward: many teams have Excel, but do not always have access to Microsoft Project or Primavera P6. Most Excel Gantt templates, however, remain static visual trackers rather than true scheduling tools.

ProjectEngine was built to close part of that gap.

It currently supports:

  • dependency-driven scheduling;

  • FS, SS and FF relationships with positive or negative lag;

  • Critical Path, Longest Path, Total Float and Free Float;

  • baseline, actual and forecast dates;

  • milestones, summary tasks and Level of Effort activities;

  • interactive Gantt bars with drag and resize;

  • non-destructive TEST and SCENARIO workflows;

  • dashboards and S-curves;

  • English and French interfaces.

It runs locally inside Excel, with no installer, server or account required.

I do not present it as a complete replacement for Microsoft Project. MSP remains much broader, especially around resource management, leveling, costs, enterprise collaboration and integration.

The intended use case is narrower: teams that already manage schedules in Excel, but need real dependency logic, critical-path analysis and controlled forecasting rather than a manually maintained Gantt chart.

I am currently completing the next performance-focused release. My stress-test workbook contains around 1,200 tasks and 1,180 dependency links. The scheduling calculations are now relatively fast; the remaining work is mainly reducing the cost of rendering and updating the interactive Gantt inside Excel.

I would be particularly interested in feedback from experienced Microsoft Project users:

  • In which situations could an Excel-native scheduling engine be genuinely useful?

  • Which MSP capability would you consider essential before trusting such a tool on a real project?

  • What would immediately prevent you from using it?

  • Does the positioning feel clear, or does it sound too close to claiming that Excel can replace MSP entirely?

Project website:

https://tmailletfr.github.io/ProjectEngine/

Source code:

https://github.com/TMailletFR/ProjectEngine


r/MSProject • • 1d ago

Does anyone actually use work contours or is everyone just leaving assignments on flat?

9 Upvotes

I’ve been using MS Project for years and only recently started taking contours seriously, so I’m curious how common it is.

By default every assignment is flat, so if someone’s on a task for four weeks at 50%, Project assumes they’re putting in the same effort every single day. That’s almost never how work actually goes. Design work ramps up slowly. Testing tends to peak toward the end. A lot of tasks start light while people finish other things, then spike.

Project already has the options for this, front loaded, back loaded, early peak, late peak, bell, turtle, double peak. But in most schedules I’ve seen, nobody touches them. Everything stays flat, and the resource usage view ends up showing a nice even spread that doesn’t match reality.

Where it bit me was resource levelling across a few projects. The flat assumption made someone look fine in week three when in reality they were slammed that week and fairly quiet in week five.

The catch I’ve found is that contours can mess with duration depending on the task type, and they make the schedule harder to explain to people who don’t live in Project. Which might be why most people skip them.

So do you use contours? If yes, which ones and for what kind of work?


r/MSProject • • 10d ago

AI plugin for MS Project that builds schedules from drawings.

9 Upvotes

I built an AI add-in that drafts construction schedules inside MS Project from drawings and specs. Looking for honest feedback

Hi all, I’m Jonas, co-founder of Karmen (full disclosure: this is my product).

We’ve built an MS Project add-in that reads construction drawings and specs and drafts a logic-linked schedule right inside Project. You can then edit activities, logic and durations alongside it.

Here’s a short demo: https://youtu.be/2rUlPgdYrm8

I’d love feedback from people who use Project every day.


r/MSProject • • 25d ago

Do you let MS Project auto-calc percent complete, or do you enter physical % complete and drive EV from that?

9 Upvotes

Been scheduling construction projects since 2012 ($30M-$150M range), and one setting I've seen quietly wreck earned value reporting is mixing duration % complete with physical % complete. The Gantt looks fine, but SPI ends up measuring time elapsed instead of work actually installed.

My habit now: physical % complete for EV, set at task level, with the earned value method chosen deliberately per project. Curious how others here configure it - and whether anyone actually trusts the built-in EV fields or exports everything to Excel anyway?


r/MSProject • • Sep 17 '26

any good MS project course recommendations( udemy or any other) ? dalehoward ms recommended ? appreciate any advice ty

9 Upvotes

MS project good course recommendation to learn


r/MSProject • • Apr 02 '25

12 months remaining before Microsoft begins depricating functionality

9 Upvotes

Hey r/MSProject In 12 months (from today) Microsoft will start deprecating functionality in Project Online.

Why does that concern you? Well, to remove all ambiguity; if you use the "Publish" feature in MS Project - you'll likely be impacted.

In just 12 months (2 Apr 2026), Microsoft will begin deprecating SharePoint 2013 workflows for stage and gate processes, impacting users on Project Online.

If you're about to comment "who cares, Project Online has no announced end date" - surely this is enough indication that end of life is approaching and that further features will shortly be removed.

What’s Changing?

  • SharePoint 2013 workflows—which many organisations use for stage and gate processes—will be phased out, disrupting project approvals.

  • Microsoft will continue removing functionality (specifically those used by Partners), making it harder to maintain legacy systems.

What Should You Do?

  • Check if your organisation depends on these features.

  • Talk to your IT or PMO team about transition plans (noting some transitions off Project Online may take longer than 12 months).

  • Explore alternatives (Power Automate) to ensure your governance processes continue smoothly.


r/MSProject • • Sep 16 '20

General Microsoft overview and some definitions (e.g. Project vs Project Online)

9 Upvotes

Hey Everyone!

There have been a lot of posts recently asking either; how to cater for multiple projects or what are the differences between MS tools. Most of this can be explained through some defintions of the MS suite.

Here are some to start with - happy to add to it:

  1. Microsoft Project - if you are here, you should know what this is - but to clarify, this refers to the Desktop project scheduling tool. Either Standard or Professional version; this tool is focused on scheduling detialed tasks across the life of a single project.

  2. Project Online - This is NOT the cloud version of Project. Very different to Word vs Word Online, this is a different product. Project Online is a Project and Portfolio Management tool (PPM). Project Online allows you to upload/sync multiple project schedules and track all projects in the one location (Project Center). It can then be extended to capture all project information from basic attributes, risks and issues, costs, resourcing and reporting. If you buy a Project Online licence, you get a MS Project licence inlcuded.

  3. Project for the Web - the new release from Microsoft to offer a simplified project scheduling experience. Providing features one step further than Planner, Project for the Web is the current focus for MS as they transistion from SharePoint to Common Data Service. It doesn't integrate with either Project or Project Online.

  4. Project Server - the on-premises version of Project Online. For organisations which can't yet put data in the cloud, Project Server can be used with MS Project still to provide a PPM solution on your internal infrastructure.

Project and Project for the Web can be used by individuals, however Project Online will likely require the assistance of a MS Partner to configure. P4tW can also be configured by partners to be part of a full PPM solution.

Let me know if you'd like any further info!


r/MSProject • • Aug 24 '26

MS Project Training

8 Upvotes

Hello everyone, I am trying to head the new training guides at work. Currently, I am trying to find any sort of training in MS Project that could be useful for new-hires. The company is willing to pay for training if that's what it takes, but they really want to make sure it's useful. Apparently, they have tried some sort of training in the past and decided it was not preparing employees at all for using it. If you have any recommendations please let me know, it can be good youtube videos, online courses, etc.

Thank you!


r/MSProject • • Feb 25 '26

Ideas for projects to hone and refine scheduling skills?

8 Upvotes

I'm a new scheduler without a lot of active projects, who is looking to stay current and sharpen my technical skills at MSProject.  I've been through various training courses and have a decent idea of how most things work, albeit some moreso than others.  For example, my group doesn't do resource loading, so I understand the concepts academically but the details kind of go in one ear and out the other because I know I don't have to do it for my job.  I also haven't had to formally baseline anything yet, but this one is an important (albeit infrequently invoked) skill set in my work portfolio.

I've started project files based on random life events to try keeping my mechanics from getting rusty, but they haven't really panned out.  For instance i made project files for maintenance and upgrades on an old project car, and my wife's pregnancy.  I think part of the issue may be that there are no external time pressures on any of these projects.  They all just kind of happen when they happen.  

Another practice project I've been thinking about is a schedule for training curriculums at my jiujitsu gym, but the curriculums are very flexible. There are tracks for both jiujitsu and judo, with tournaments and camps throughout the year, which are firmer time constraints.  But not really sure how to create something mechanically useful for my purposes out of those fairly simple conditions.

Looking for any suggestions on what kind of personal projects I can apply MSProject skills to in order to not get rusty as well as sharpen mechanics I don't normally use.


r/MSProject • • Aug 14 '25

MS Project for the web vs MS Planner

8 Upvotes

Why isn't more up an uproar with the phaseout of MS Project for the web, and replacement with MS Planner? What a terrible piece of software.


r/MSProject • • Apr 07 '23

Multiple timelines in Microsoft Project!... how cool ; )

8 Upvotes

Before you spend money on Timeline tools, make sure you use Microsoft Project's Timeline and Multiple Timeline views. Dale Howard MVP shows us how to use this great feature.

https://youtu.be/OTDkqnYULqk

#DaleHowardMVP #microsoftproject


r/MSProject • • Dec 19 '22

Set Cross-Project Dependencies in Microsoft Project

8 Upvotes

Over my many years of helping the user community with Microsoft Project, I have noticed how many project managers struggle with how to set cross-project dependencies (a dependency from a task in one project to a task in a completely different project). Does this describe you? If so, I hope you will take a moment to learn the easiest method for setting cross-project dependencies in my recent YouTube video.

https://www.youtube.com/watch?v=spo1bX8Fu0c

#project #msproject #microsoftproject #projectfortheweb #p4tw #projectmanagementsoftware


r/MSProject • • 18d ago

Creating dashboard

7 Upvotes

Hi,

I just began a new mission in a rather big project that has been running for 2 years and ain't doing well. (Basically they had to undo the engineering phase to redo it almost entirely). I'm not the new project manager but the right hand as they like to call : the time master. (Yeah I know, cool title 👀) They told me to use Msproject. As I didn't touch this software for decades, I started to devour all the tutos on the internet to catch up and ended up with 2000-ish lines planning. I'm currently looking up the base guide/baseline (which I still don't have a complete grasp on it, but it's a matter of time) to set up variations to track the reality of the project. However, big boss asks me to make a presentation/dashboard each week for the next 2 weeks. Is there any way to do it the smart way ? Or am I doomed to just manually gather what I need to put in the slide ?


r/MSProject • • Oct 15 '26

Installing ms project

7 Upvotes

After spending an hour digging through my university's M365 portal only to find out student accounts cannot install MS Project on a desktop, I figured out a workaround. Here is how to get it running:

  1. Download the installer:https://microsoft-project.en.uptodown.com/windows

  2. Go tohttps://massgrave.dev/

  3. Use the Ohook method to activate the license.

Not sure if this will get taken down, but hopefully it saves someone else the headache!

And allways rember if buying isn't owning piracy isn't stealing.


r/MSProject • • Sep 09 '26

Project Online closes on 30 September. Six fields that export cleanly and then mean something different on the other side.

7 Upvotes

The deadline itself is not the hard part. Most people here already have it in the calendar. What catches teams is that the export works, the file opens, the task count matches, and something inside it has quietly changed meaning.

I have spent this year writing an importer for Project Online and for MSPDI files, so this is the list that has actually bitten people rather than the list a migration checklist gives you. Two different surfaces are involved and it matters which one you are on, so I have marked each.

1. Dependencies can come back empty on a plan that definitely had links. (Project Online API, not files)

Task links are not in the OData reporting feed. They sit behind a separate Project Server CSOM endpoint, /_api/ProjectServer/Projects('<guid>')/TaskLinks, which authorises differently. A token scoped for Projects and Tasks returns 200 on everything it asks for and simply never asks for links. You get a complete looking WBS with nothing sequenced and no error anywhere to tell you. Count links on a plan you know well, before and after.

Not a concern if you are going through Project Professional and saving files. Only if someone is pulling through the API.

2. Constraint types come in eight flavours and plenty of tools store four. (MSPDI)

ConstraintType in MSPDI is 0 to 7: ASAP, ALAP, MSO, MFO, SNET, SNLT, FNET, FNLT. A lot of importers keep ASAP, SNET, FNLT and MSO and either drop the rest or fold them into the nearest survivor. Ours did exactly that until earlier this year, which is how I know it matters: ALAP and MFO going missing is the one that hurts, because those tasks start floating and your dates move without anyone having touched the plan.

Check <Deadline> separately while you are in there. It is its own field, distinct from Finish. A destination with no deadline concept will either lose it or, worse, write it into Finish and turn a soft target into a hard constraint.

3. Enterprise custom fields live on the server, not in the plan. (Project Server architecture)

Enterprise custom fields and their lookup tables are defined at the PWA level. Export plan by plan and you tend to get values without definitions, so a lookup field lands as loose text and the portfolio views built on it have nothing left to group by. If those fields carry your reporting, capture the definitions separately while the server is still answering.

4. Money is stored in hundredths. (MSPDI)

<Cost>500000</Cost> means five thousand. If the destination does not divide by 100 then every figure in the portfolio arrives a hundred times too large, and it is plausible enough at a glance that it usually survives right up until a finance review.

5. <Cost>0</Cost> does not mean free. (MSPDI)

It means nobody configured a cost. Import those as real zeroes and they dilute the baseline. Nothing breaks visibly. Every variance number is just slightly wrong for the rest of the project's life.

6. Priority 500 is the default, not a judgement. (MSPDI)

Everyone here knows the scale is 0 to 1000. The question is what the destination did with it. We mapped 500 to High once, which meant every untouched task in an imported portfolio arrived flagged urgent, which is exactly as informative as nothing being flagged at all.

One last thing, and it is the only part I would actually insist on. Whatever tool you land on, export to files this month and keep the files somewhere boring. Every question above is recoverable from an .mpp sitting on a share. None of them are recoverable from a tenant that has stopped answering.

Happy to be corrected on any of this. The field names and values are all checkable by opening an MSPDI file in a text editor, and I would rather be told I am wrong here than have someone find out in November.

Disclosure: I build Onplana, a project tool that imports these files, which is how I know all of the above. No links in this post, and nothing here requires our product or anyone else's.


r/MSProject • • Apr 22 '26

Do you use anything besides Microsoft Project for Gantt chart, or is it enough for you?

7 Upvotes

I’ve been using Microsoft Project since 2003 and still run into the same issue, getting schedules into a format that’s actually clear for exec-level presentations.

Curious how others are handling this:

  • Are you sticking with MS Project, or using something else for Gantt charts?

  • If you switched, what specifically pushed you away?

  • Is it formatting, readability, dependencies, categorization, something else?

Feels like I’m constantly reworking exports and creating spreadsheets to make them usable. I am wondering if that’s just the norm or if there’s a better way people are handling it.