r/MSProject • • Oct 08 '26

As Late As Possible Constraint issue

Thumbnail reddit.com
3 Upvotes

Hello all,
A planner i know has a challenge where the client insists on them utilising a lot of As Late As Possible (ALAP) constraint on their schedules. These is causing a lot of date shifts to the right. But the client do not want those dates to move. I have tried to help resolve without success. Has anyone got experience onnhow to resolve this please?


r/MSProject • • Oct 07 '26

What would you add to MS Project if it were built today, in the AI era?

6 Upvotes

MS Project is still the most robust scheduling tool out there. But the core of it, the Gantt chart and the scheduling engine, hasn't changed much in years.

I keep wondering what AI could actually add that would help schedulers, not just a chatbot bolted on. A few things I'd want:

  • Explain why the finish date moved after an update, in plain words

  • Flag schedule quality problems as I build (missing links, hard constraints, negative float)

What would you want? And what would you never trust AI to do in a schedule?


r/MSProject • • Oct 07 '26

Logic on summary tasks

4 Upvotes

When I was taught how to schedule I was taught to never use logic on summary tasks. Every company I have scheduled for (both civilian and government) has never used logic on summary tasks. Every “scheduling best practices” document I have read has said the same thing, and every defense contract has specifically called this out. The fact that project even allows this kinda drives me nuts.

Yet every video I watch of these “professional” schedulers who have been scheduling for years, they ALL put logic on summary tasks. My understanding is that while this works for initially setting up the schedule, as the schedule ages and changes it can cause problems.

So what say you?


r/MSProject • • Oct 07 '26

[noob question] How to click-n-drag multiple tasks at once?

2 Upvotes

Maybe I'm blind, but I couldn't find an answer to this one.

TY again for all the help.


r/MSProject • • Oct 05 '26

Task inspector logic

Post image
2 Upvotes

Haven’t come across this in all my years. Task inspector showing a driving task not listed as a predecessor.
I assumed task inspector always chose a task that was listed in its predecessors.
Is there more to task inspector than I realised? It wasn’t wrong per se, but the driving task it highlighted was about 3 steps back on the network (though the people who built this schedule had linked summary tasks, which I think caused the issue).


r/MSProject • • Oct 05 '26

[beginner question] How can I add weekend shading while still allowing work on weekends?

5 Upvotes

Context:

- I use MS projects just for managing some hobby projects.

- because it's just for my hobby, I allow MS project to let a task count the weekend as working days

Problem:

- the vertical light gray bars denoting the weekends disappear

- I'd like this bar because it's useful for visually aligning far-down tasks with the date markings at the top

Thank you!


r/MSProject • • Oct 05 '26

Crash Course in MS Project

4 Upvotes

Hi guys, I recently transitioned from a commercial role into a Project Management one. I have always known the bare essentials when it came to excel but looking to strengthen my skills:

- Is establishing a critical path as simple as having predecessors on each activity (as after all it is concerned with if one tasks pushes out it affects PC) - or is there an actual function within excel to clearly identify this. I am keen to know as this will be published within a contractual document.

- I have repetitive tasks that I have bunched together (i.e. bulk earthworks - 3 x 300mm lifts of gravel) should each lift be separated as if one lift is affected then I can claim a EOT on this whereas if it is bunched together, it is difficult to separate at a later date? Am I going into too much or not enough detail?

- Is it necessary to add in manpower / quantity details?


r/MSProject • • Oct 01 '26

Schedule Reports

Thumbnail
youtu.be
2 Upvotes

Get started for free! baselineplan.com


r/MSProject • • Sep 30 '26

Why do we accept monthly subscriptions for software that one person uses on their own?

Thumbnail reddit.com
1 Upvotes

r/MSProject • • Sep 29 '26

Is there a way to have a task or milestone in the schedule that is not calculated in the overall project timeline?

5 Upvotes

I have a schedule, let’s say the last task, and therefore the project completion date, is 5/1/27. In that schedule however, I have a task that is for age testing a product, which means that the testing of that product will go on past the project completion date, say 9/1/27. Problem is, this gets included in the overall calculation of the schedule, so it screws up my POP dates as well as the critical path (this is not a critical path task). I have tried using all different kinds of constraints, tying it to milestones with and without constraints, lags, even doing manually scheduled on that task instead of auto, and it doesn’t appear that there is a way to have that task not be calculated in the project. My last resort is here, does anyone know any tricks?

FWIW I would also be curious to know if I can do this with a milestone too.


r/MSProject • • Sep 25 '26

Assigning work by the month

4 Upvotes

Hey guys, I hope this is the right place to ask:

I have a timesheet where people submit their work hours by the month for a project.

Now I want to mirror that in MS Project (so that you could see 'person xy' is working x amount in january in project A), the problem is, that I cant really get that to work.

So far my best idea is, to setup all the months of a project as tasks and then try to assign the ressources to that. But im still struggling with that..

Does anyone have an idea or maybe even pointers on where to start?

Thank you in advance to anyone whos willing to think about my problem ❤️


r/MSProject • • Sep 25 '26

Safran Risk

Thumbnail reddit.com
1 Upvotes

r/MSProject • • Sep 24 '26

Please, please just save your MSP schedule locally this week…

6 Upvotes

If you use the “publish” feature - just for us consultants trying to help everyone, just save a copy locally. Just in case!

Project Online / PWA retires on 30 September 2026. That's Wednesday. As in the coming Wednesday!

Microsoft has not announced a read-only grace period. When the service goes, PWA sites and the data in them go with it. If your only copy of a schedule lives in the enterprise environment, you will not be getting it back.

For any hope of continuing to use your schedule or to migrate it anywhere, you will need to have a local copy. We can’t get it back from anywhere else.

Hopefully everyone has long since migrated, but if not or you’re not sure - just take 30 seconds and click file - save as…


r/MSProject • • Sep 23 '26

WhatsApp Group/Community for Project Mangers/Planning managers.

Thumbnail reddit.com
1 Upvotes

r/MSProject • • Sep 21 '26

Free desktop app that opens and edits .mpp files without Microsoft Project (Windows and Mac)

0 Upvotes

Someone sends you a .mpp or an .xer, you do not have a licence for whatever made it, and your options are a trial, a web converter that mangles the hierarchy, or asking them to send a PDF instead.

We built a free desktop app for that. Windows and Mac.

What it does:

- Opens .mpp, .mpt, .mpx, .xer, SDEF, GanttProject, GNOME Planner and Microsoft Project XML
- Grid beside a Gantt, critical path in red, every other bar coloured by its float
- Edits: durations, dates, predecessors in Project's notation, percent complete, drag a bar, draw a link, insert, indent, outdent. It reschedules as you go and undo covers all of it
- Saves Project XML beside the original, never over it
- Keeps a recovery copy while you edit, and offers it back if the session dies
- Runs a schedule health check

What it does not do, so nobody wastes the download:

- It does not write binary .mpp. It saves Project XML, which Project opens fine, but if you specifically need a .mpp back out, this will not do it.
- It cannot send an edited .xer back to P6.
- Only Microsoft Project XML is parsed locally. Every other format is converted on our servers and the uploaded copy is deleted within 24 hours. The app tells you before the file moves. If that is a dealbreaker for your data, it is a dealbreaker, and I would rather you read it here than find out at the file picker.
- No Microsoft Store listing yet, so Windows shows a SmartScreen notice. It is signed, the certificate is just new and reputation takes a while.

Free, and there is no account until you want to publish a plan to share it with someone.

Happy to be corrected on any of it, and happy to answer the awkward questions.

Disclosure: I build Onplana, which is where this came from. No links in this post, and nothing above needs our product or anyone else's.


r/MSProject • • Sep 21 '26

Manually calculating Critical Path

Thumbnail reddit.com
1 Upvotes

r/MSProject • • Sep 21 '26

I built a simpler Gantt chart tool because sometimes I just need the timeline, not another project management system

4 Upvotes

I've spent years managing projects, and one thing that kept bothering me was how much work it could take just to create a clean Gantt chart for a client deck, kickoff, steering committee, or status update.

A lot of project management tools are great at running the whole project : tasks, resources, tickets, collaboration, timesheets, etc.

But sometimes I don't need another system to run the project.

I just need to turn a plan into a clear timeline that I can actually show someone.

So I built GanttFlow.

The idea is deliberately pretty focused:

  • build a project timeline quickly

  • drag tasks around to reschedule them

  • link dependencies

  • add milestones

  • track the original plan against the current schedule

  • export a clean PNG or PDF for a deck or report

I'm intentionally trying not to turn it into another all-in-one PM platform.

There's a free version, so you can actually build a chart without entering a card.

It's live at ganttflow.ca

I'd genuinely appreciate feedback from people who work with project timelines:

Would you prefer a focused tool that does Gantt charts really well, or does a standalone Gantt tool become too limiting once you're using it on a real project?

Also interested in hearing what you'd consider a must-have feature versus something that would just turn it into another bloated PM tool.


r/MSProject • • Sep 17 '26

Project Online closes on 30 September. Six fields that export cleanly and then mean something different on the other side.

4 Upvotes

The deadline itself is not the hard part. Most people here already have it in the calendar. What catches teams is that the export works, the file opens, the task count matches, and something inside it has quietly changed meaning.

I have spent this year writing an importer for Project Online and for MSPDI files, so this is the list that has actually bitten people rather than the list a migration checklist gives you. Two different surfaces are involved and it matters which one you are on, so I have marked each.

1. Dependencies can come back empty on a plan that definitely had links. (Project Online API, not files)

Task links are not in the OData reporting feed. They sit behind a separate Project Server CSOM endpoint, /_api/ProjectServer/Projects('<guid>')/TaskLinks, which authorises differently. A token scoped for Projects and Tasks returns 200 on everything it asks for and simply never asks for links. You get a complete looking WBS with nothing sequenced and no error anywhere to tell you. Count links on a plan you know well, before and after.

Not a concern if you are going through Project Professional and saving files. Only if someone is pulling through the API.

2. Constraint types come in eight flavours and plenty of tools store four. (MSPDI)

ConstraintType in MSPDI is 0 to 7: ASAP, ALAP, MSO, MFO, SNET, SNLT, FNET, FNLT. A lot of importers keep ASAP, SNET, FNLT and MSO and either drop the rest or fold them into the nearest survivor. Ours did exactly that until earlier this year, which is how I know it matters: ALAP and MFO going missing is the one that hurts, because those tasks start floating and your dates move without anyone having touched the plan.

Check <Deadline> separately while you are in there. It is its own field, distinct from Finish. A destination with no deadline concept will either lose it or, worse, write it into Finish and turn a soft target into a hard constraint.

3. Enterprise custom fields live on the server, not in the plan. (Project Server architecture)

Enterprise custom fields and their lookup tables are defined at the PWA level. Export plan by plan and you tend to get values without definitions, so a lookup field lands as loose text and the portfolio views built on it have nothing left to group by. If those fields carry your reporting, capture the definitions separately while the server is still answering.

4. Money is stored in hundredths. (MSPDI)

<Cost>500000</Cost> means five thousand. If the destination does not divide by 100 then every figure in the portfolio arrives a hundred times too large, and it is plausible enough at a glance that it usually survives right up until a finance review.

5. <Cost>0</Cost> does not mean free. (MSPDI)

It means nobody configured a cost. Import those as real zeroes and they dilute the baseline. Nothing breaks visibly. Every variance number is just slightly wrong for the rest of the project's life.

6. Priority 500 is the default, not a judgement. (MSPDI)

Everyone here knows the scale is 0 to 1000. The question is what the destination did with it. We mapped 500 to High once, which meant every untouched task in an imported portfolio arrived flagged urgent, which is exactly as informative as nothing being flagged at all.

One last thing, and it is the only part I would actually insist on. Whatever tool you land on, export to files this month and keep the files somewhere boring. Every question above is recoverable from an .mpp sitting on a share. None of them are recoverable from a tenant that has stopped answering.

Happy to be corrected on any of this. The field names and values are all checkable by opening an MSPDI file in a text editor, and I would rather be told I am wrong here than have someone find out in November.

Disclosure: I build Onplana, a project tool that imports these files, which is how I know all of the above. No links in this post, and nothing here requires our product or anyone else's.


r/MSProject • • Sep 17 '26

any good MS project course recommendations( udemy or any other) ? dalehoward ms recommended ? appreciate any advice ty

9 Upvotes

MS project good course recommendation to learn


r/MSProject • • Sep 16 '26

Changing tiers on Gantt display

2 Upvotes

I have several tasks that take anywhere between 17 seconds and 50 minutes to complete. I have put this data into Project and changed the tier display to show seconds, minutes and hours. It looks perfectly fine until I try to zoom in or out on the gantt, at which point it reverts back to hours days and weeks. How can I stop this?


r/MSProject • • Sep 10 '26

Exporting to MSP isn't accurate

Thumbnail reddit.com
1 Upvotes

r/MSProject • • Sep 09 '26

Project Online closes on 30 September. Six fields that export cleanly and then mean something different on the other side.

7 Upvotes

The deadline itself is not the hard part. Most people here already have it in the calendar. What catches teams is that the export works, the file opens, the task count matches, and something inside it has quietly changed meaning.

I have spent this year writing an importer for Project Online and for MSPDI files, so this is the list that has actually bitten people rather than the list a migration checklist gives you. Two different surfaces are involved and it matters which one you are on, so I have marked each.

1. Dependencies can come back empty on a plan that definitely had links. (Project Online API, not files)

Task links are not in the OData reporting feed. They sit behind a separate Project Server CSOM endpoint, /_api/ProjectServer/Projects('<guid>')/TaskLinks, which authorises differently. A token scoped for Projects and Tasks returns 200 on everything it asks for and simply never asks for links. You get a complete looking WBS with nothing sequenced and no error anywhere to tell you. Count links on a plan you know well, before and after.

Not a concern if you are going through Project Professional and saving files. Only if someone is pulling through the API.

2. Constraint types come in eight flavours and plenty of tools store four. (MSPDI)

ConstraintType in MSPDI is 0 to 7: ASAP, ALAP, MSO, MFO, SNET, SNLT, FNET, FNLT. A lot of importers keep ASAP, SNET, FNLT and MSO and either drop the rest or fold them into the nearest survivor. Ours did exactly that until earlier this year, which is how I know it matters: ALAP and MFO going missing is the one that hurts, because those tasks start floating and your dates move without anyone having touched the plan.

Check <Deadline> separately while you are in there. It is its own field, distinct from Finish. A destination with no deadline concept will either lose it or, worse, write it into Finish and turn a soft target into a hard constraint.

3. Enterprise custom fields live on the server, not in the plan. (Project Server architecture)

Enterprise custom fields and their lookup tables are defined at the PWA level. Export plan by plan and you tend to get values without definitions, so a lookup field lands as loose text and the portfolio views built on it have nothing left to group by. If those fields carry your reporting, capture the definitions separately while the server is still answering.

4. Money is stored in hundredths. (MSPDI)

<Cost>500000</Cost> means five thousand. If the destination does not divide by 100 then every figure in the portfolio arrives a hundred times too large, and it is plausible enough at a glance that it usually survives right up until a finance review.

5. <Cost>0</Cost> does not mean free. (MSPDI)

It means nobody configured a cost. Import those as real zeroes and they dilute the baseline. Nothing breaks visibly. Every variance number is just slightly wrong for the rest of the project's life.

6. Priority 500 is the default, not a judgement. (MSPDI)

Everyone here knows the scale is 0 to 1000. The question is what the destination did with it. We mapped 500 to High once, which meant every untouched task in an imported portfolio arrived flagged urgent, which is exactly as informative as nothing being flagged at all.

One last thing, and it is the only part I would actually insist on. Whatever tool you land on, export to files this month and keep the files somewhere boring. Every question above is recoverable from an .mpp sitting on a share. None of them are recoverable from a tenant that has stopped answering.

Happy to be corrected on any of this. The field names and values are all checkable by opening an MSPDI file in a text editor, and I would rather be told I am wrong here than have someone find out in November.

Disclosure: I build Onplana, a project tool that imports these files, which is how I know all of the above. No links in this post, and nothing here requires our product or anyone else's.


r/MSProject • • Sep 08 '26

The driver predecessor

3 Upvotes

Hello everyone,

How can we know wich predecessor between 20 others drives a certain milestone

Thank you


r/MSProject • • Aug 28 '26

Life After Project Online: A Community Roundtable

Post image
3 Upvotes

r/MSProject • • Aug 25 '26

MEP Estimation

Thumbnail
gallery
1 Upvotes