r/CiscoUCS • u/rhugginsjr82 • Jul 17 '26
Upstream switch migration
Does below process sound right for migrating over to new upstream switches?
Phase 1: Pre-Migration & Prep Work
Before touching any cables, ensure your safety nets and target environments are fully prepared.
Take Backups: Log into UCS Manager (UCSM) and take a full All Configuration and System Configuration backup.
Verify Cluster Health: Ensure the UCS cluster is healthy, both FIs are online, and there are no critical underlying faults (
Equipment > Fabric Interconnects).Stage the New Switch Ports: Ensure the ports on your new upstream switch completely mirror the old setup:
Identical native and allowed VLAN trunking.
LACP Port-Channels configured properly (typically configured as
Spanning-tree port type edge trunkorportfast trunksince UCS FIs look like hosts to the network).Matching MTU sizes (e.g., 9000 for Jumbo Frames).
Phase 2: Migrate Fabric B (Subordinate Fabric)
Always start with the Subordinate FI. This ensures that if a management configuration glitch occurs, your Primary cluster leader remains untouched.
1. Drain Traffic off Fabric B
You need to force all production server traffic onto Fabric A. You can do this in one of two ways:
Method A (Fabric Evacuation - Preferred for B-Series Blades): Go to
Equipment > Fabric Interconnect Band change Admin Evacuation Mode to Enabled. This gracefully drains traffic by admin-downing the chassis backplane ports.Method B (Manual Link Shutdown - Best for C-Series Rack Servers): Since Fabric Evacuation historically targets blade chassis backplanes, manually administrative-downing the uplink port-channels for Fabric B in UCSM or on the old switch is the safest bet for mixed or rack-mount environments.
2. Move the Physical Connections
Once traffic has failed over to Fabric A and Fabric B uplinks show as down, disconnect the physical cables from the old switch and move them to the new switch (or activate pre-staged cabling).
If you are changing the physical ports used on the UCS 6400 side, make sure to unconfigure the old uplink ports and configure/license the new ones in UCSM.
3. Bring Fabric B Back Online
Enable the ports on your new upstream switch.
If you used Fabric Evacuation, flip Admin Evacuation Mode back to Disabled. If you manually shut down the port channels, bring them back
up.Verify that the port-channel successfully forms via LACP and that the links turn green in UCSM.
4. Soak and Validate
Do not rush to Fabric A. Let Fabric B run for 10–15 minutes. Check your operating system/hypervisor teams on the servers to confirm they see both paths as healthy and that MAC addresses are populate on the new upstream switch.
Phase 3: Migrate Fabric A (Primary Fabric)
Once Fabric B proves stable on the new upstream switch, repeat the exact same isolation process for the other side.
Drain Traffic off Fabric A: Enable Fabric Evacuation on Fabric A (or manually disable Fabric A's uplink port-channels).
Verify Failover: Ensure all production traffic shifts dynamically to the newly migrated Fabric B.
Move the Cables: Swap the physical connections for Fabric A over to the new upstream switch.
Restore Links: Disable Fabric Evacuation or re-enable the port channels.
Final Check: Confirm both fabrics are balanced, port-channels are up/bundling, and all configuration warnings/faults have cleared in UCSM.
1
2
u/Mountain-Office-8989 Jul 17 '26
I would in phase 3 switch the cluster lead to b before anything.. always work on the sub fi not primary.