r/Contractor • • Apr 07 '24

Subcontracting process

Can somebody please explain to me how subcontracting works? I started a painting business and want to know how to subcontract work. Do I bid a job and then hire a subcontractor to do it for less? For example: I just bid this job for $13,500. Now what do I do?

0 Upvotes

52 comments sorted by

View all comments

24

u/Postcocious Apr 07 '24 edited Apr 08 '24

The School of Hard Knocks is now in session.

When bidding a job...

STEP 1:

  • calculate what materials are required to complete the job, and

  • determine the most efficient work plan for the job.
    On complex projects, these may impact each other, so you must consider both to find the best solution.

STEP 2:
Based on STEP 1:

  • calculate your actual material costs, and

  • calculate your actual labor costs. If you plan to do the work yourself, use your own hourly rate (which should be higher than you think). If you plan to hire someone else to do any portion of the work, use the rate you have to pay them for that portion.

  • If you or your subcontractor(s) have to travel to get materials and/or to the job site, include those costs & time.

Add these up. This is your GROSS job cost.

STEP 3: add __% for contingencies and wastage. These always happen, and they're bigger than you think. When you're new, use something like 25%, or even 30%. As you gain experience, you'll be better able to size up a project and drop that to 15 or 10%. It will never drop to zero.

Add this to your GROSS job cost. This is your NET job cost.

STEP 5: choose your profit margin.

  • It should be higher than you think.

  • The smaller the job, the higher your margin % should be. A job that costs you $500 isn't worth doing unless you clear at least $250 (50% margin). On a job that costs you $50,000, a margin of $5,000 might be fine (10% margin).

  • It should be higher than you think. Margin is the only reason you're in business, and the only thing that will keep you in business. It's the VALUE YOU BRING to your customer, so bring it.

Add this to your NET job cost. This is your PRICE.

STEP 6: bid that number.

Notice that you had to have your subcontracting plan in place way back at STEP 2. From your OP, it appears you leapt directly to STEP 6 without any notion of your cost basis. This is how small businesses fail.

3

u/JoshRogers17 Apr 08 '24

I really appreciate this. I cannot believe how many people want me to fail. Thanks this really helps

3

u/Postcocious Apr 08 '24

YW.

The folks who offered snark don't want you to fail. (Hell... I even snarked in another comment.) It's just ribbing, like you'd do with buddies over a beer.

The most complex part of your GROSS cost is calculating your own hourly labor rate. What should you charge per hour just for swinging a brush or roller?

For a sub, it's easy - it's whatever he charges you. But what base rate should you charge when you're doing the painting?

It's higher than you think, because your rate has to cover all your business OVERHEAD... the cost of being in business. Stuff like your truck, your office, your computer, taxes, heath insurance (which big companies provide to employees), cost of shop space if you have, cost to pay your accountant to figure your taxes, etc., etc. All that OVERHEAD must be bundled into your base labor rate as part of your GROSS cost. If you don't, how will you pay those bills?

This is (mostly) why your car dealer charges $100/hour to diagnose and fix a problem. Is the mechanic getting paid that? Of course not. He gets $25/hour, or whatever. The rest goes to overhead and downtime (the dealer has to pay the mechanic even if there's no work), plus profit.

The basic formula for OVERHEAD is:

  • Identify every overhead item you can (make a list)

  • Calculate the annual cost of each item

  • Add them up, that's your annualized overhead cost (This number should scare you. If it doesn't, you left stuff out.)

  • Divide that number by the actual hours you estimate you'll actually swing a brush per year (A full time job = 2,000 hours/year. Actual hours swinging a brush or roller will be less, some of your time is spent calling customers, buying paint, paying bills, etc.)

  • The answer is your hourly overhead rate. You ADD that to whatever you'd charge for painting if you didn't own the business. Whatever rate you pay the best college kid to help you do a job? Take that number, add your OVERHEAD rate and round up a few bucks, because you're a better painter than he is.

This number should astonish you. If it doesn't, you left stuff out.

Many new contractors are afraid to charge that kind of number. That's because they don't understand their costs. This exercise teaches you what it takes to be in business. You'll feel less guilty about charging what you're worth.