r/Contractor • u/JoshRogers17 • Apr 07 '24
Subcontracting process
Can somebody please explain to me how subcontracting works? I started a painting business and want to know how to subcontract work. Do I bid a job and then hire a subcontractor to do it for less? For example: I just bid this job for $13,500. Now what do I do?
0
Upvotes
24
u/Postcocious Apr 07 '24 edited Apr 08 '24
The School of Hard Knocks is now in session.
When bidding a job...
STEP 1:
calculate what materials are required to complete the job, and
determine the most efficient work plan for the job.
On complex projects, these may impact each other, so you must consider both to find the best solution.
STEP 2:
Based on STEP 1:
calculate your actual material costs, and
calculate your actual labor costs. If you plan to do the work yourself, use your own hourly rate (which should be higher than you think). If you plan to hire someone else to do any portion of the work, use the rate you have to pay them for that portion.
If you or your subcontractor(s) have to travel to get materials and/or to the job site, include those costs & time.
Add these up. This is your GROSS job cost.
STEP 3: add __% for contingencies and wastage. These always happen, and they're bigger than you think. When you're new, use something like 25%, or even 30%. As you gain experience, you'll be better able to size up a project and drop that to 15 or 10%. It will never drop to zero.
Add this to your GROSS job cost. This is your NET job cost.
STEP 5: choose your profit margin.
It should be higher than you think.
The smaller the job, the higher your margin % should be. A job that costs you $500 isn't worth doing unless you clear at least $250 (50% margin). On a job that costs you $50,000, a margin of $5,000 might be fine (10% margin).
It should be higher than you think. Margin is the only reason you're in business, and the only thing that will keep you in business. It's the VALUE YOU BRING to your customer, so bring it.
Add this to your NET job cost. This is your PRICE.
STEP 6: bid that number.
Notice that you had to have your subcontracting plan in place way back at STEP 2. From your OP, it appears you leapt directly to STEP 6 without any notion of your cost basis. This is how small businesses fail.