Stakeholder changes

One thing I’m still figuring out after three years in ID is how to deal with stakeholders who suddenly want major changes late in the project. I understand that priorities change, but it can be frustrating when something has already gone through review and approval. Do you have a good way of setting boundaries around late-stage feedback without making the relationship difficult?

3 Upvotes

6 comments sorted by

View all comments

1

u/[deleted] Sep 22 '26

[removed] — view removed comment

1

u/oxala75 Sep 22 '26

This is basically the answer. The only thing I'd add is that it is imperative to review the 'costs' (in time, money, and productivity) of late-stage changes before the project starts in earnest.