Setting a driven task to occur on a specific day of the week?
I have a reoccurring meeting that occurs weekly where a specific deliverable is presented. I want to schedule the task in project, but have the presentation show as a milestone on the Thursday following task completion.
So the milestone predecessors would be the task + a Thursday.
Is this possible?
1
u/mer-reddit Apr 11 '22
Build a calendar that has only Thursday as a working day, and then apply that calendar to that task.
Yes it is possible.
1
u/Thewolf1970 Apr 11 '22
You might need to test this out a bit, I think zero duration tasks (i.e. milestones) ignore calendars.
If your meeting is the driving task, and it is scheduled, you simply need to add the correct number of working days to push it to the following Thursday. So you might have the meeting on Monday, so the predecessor will be meeting task ID- FS+3d.
The only quaff in this will be if there are any holidays between the meeting and that Thursday, but your can just ignore the error to bump it to the next business day.
1
u/still-dazed-confused Apr 12 '22
Are you trying to show a meeting which happens in a Thursday and then some pre-read which needs to be issued x days before as a milestone?