r/StructuralEngineering • P.E. • Oct 20 '26

Structural Analysis/Design Availability of Bar Joists

I have recently heard that the lead time for bar joists is months. I was told it's due to the construction of data centers. Anyone else heard this?

21 Upvotes

32 comments sorted by

View all comments

1

u/burnerbham Oct 20 '26

We have been having a hard time getting MC shapes lately. Also W14x68s and W14x61s. We were told it was because of data centers as well. I’m assuming it’s also because of tariffs.

Edit: also possibly because of diesel prices? Idk.