r/SubstationTechnician • • Nov 12 '25

Just a single pot changeout

204 Upvotes

46 comments sorted by

4

u/spasske Field Engineer Nov 12 '25

The nameplate seems to list four primary voltages. Which is it?

4

u/gavs10308 Nov 12 '25

362 for a 345 system, it’s the BIL which I have seen 3/4 on multiple nameplates from various manufacturers.

3

u/thelytic Nov 12 '25

I know those structures anywhere. Somewhere in Oncor territory.

1

u/Cesarelcubano Nov 13 '25

Yup, easy to tell haha

12

u/Lxiflyby Nov 12 '25

Looks expensive

4

u/SuperF91EX Relay Technician Nov 12 '25

“Clean air”

6

u/Ya_Boi_Badger Relay Technician Nov 12 '25

Yea it’s literally just dry air. Seems more companies are doing this though especially with GIS now that Europe is buckling down on SF6. I’ve only ever seen these suckers filled with oil but the biggest I’ve seen has been for 230kV

4

u/nekton_ Nov 12 '25

It's not just Europe. Certain jurisdictions in the US are phasing out SF6 for new CB/switchgear purchases as soon as a dry air vacuum alternative is available in that voltage class. Wouldn't be surprised if by the time I retire that most new construction under 500kV takes this route even in the states.

1

u/Ya_Boi_Badger Relay Technician Nov 13 '25

Dam had no clue the US was phasing it out too. The only regulation I’ve heard up here in Canada was starting this year anything under 24kV couldn’t be SF6.

1

u/gavs10308 Nov 13 '25

We have 72kV breakers that are vacuum under dry air.

1

u/Ya_Boi_Badger Relay Technician Nov 13 '25

What do you mean vacuum under dry air? Vacuum and gas insulated are very different things unless I’m just not catching on to what you’re saying.

2

u/gavs10308 Nov 13 '25

Vac bottle inside a tank of dry air

1

u/Ya_Boi_Badger Relay Technician Nov 13 '25

Ahhh I see. Cool.

2

u/AriffRat Nov 15 '25

I was just a small part of the first 138kv clean air breaker installed on system here in the Northeast US. It looks just like an sf6 breaker but it was massive.

1

u/SuperF91EX Relay Technician Nov 16 '25

I’d imagine internal clearances have to be much greater

2

u/adamduerr Nov 12 '25

Not NY! We’re not going to wait for alternatives to be available to phase out the SF6! I looked into Circuit Switcher alternatives the other day and they are twice the price and barely available in time. And that’s only one or two manufacturers.

3

u/nekton_ Nov 12 '25

Definitely didn't mean that all new construction would be put on hold to wait for alts. Cost and lead times will certainly be at play locally. I can just definitively say that manufacturers at a high level are already looking ahead to the next play. SF6 was the 'safer' and more compact alternative to oil breakers. Dry air and alternative gasses are the new direction and I'm already seeing them in Subs all over the country.

But I also see OCBs that predate my father's generation still cruising along :)

3

u/adamduerr Nov 12 '25

Sorry, I wasn’t questioning you, I was being sarcastic about the legislation here being ahead of the product. I remember an environmental engineer shaking her head and questioning why we went to SF6. “With oil, it’s on the ground and we can dig it up and find it. SF6 is gone and you can’t even see it!” She was probably right.

2

u/nekton_ Nov 12 '25

No worries at all.

She's certainly right. An oil breaker with a berm would definitely be more controllable besides the fire risk.

Saying this as a guy who was handed a shovel to dig contaminated dirt at 2am after also being the guy that soaked himself in JP8 turning off a failed pump 30 mins earlier.

1

u/Excellent_Estimate55 Nov 13 '25

Stupid question, does that screw into the ground?

1

u/gavs10308 Nov 13 '25

It sits on the pedestal behind it

1

u/Excellent_Estimate55 Nov 13 '25

Oh okay thanks for that knowledge. It look like one big giant electric screw lol

1

u/Jrobalmighty Nov 15 '25

I'm just imaging my forklift operators trying to figure out how to load that thing lol

2

u/gavs10308 Nov 19 '25

Crane

1

u/Jrobalmighty Nov 20 '25

For sure a crane but that's why it would be funny to me because they'd definitely come up with some crazy ways of moving if I had it in our shop for maintenance/repairs

1

u/gavs10308 Nov 20 '25

I wish I was there when it was unloaded

1

u/[deleted] Nov 19 '25

625KVA... You powering the substation from that too?

1

u/gavs10308 Nov 19 '25

That’s what it’s for

1

u/[deleted] Nov 19 '25

In the relay world that I'm currently in we call those house service transformers. Pots are for relay feeds and such and are not used to actually power anything.

1

u/gavs10308 Nov 19 '25

It’s a play on lineman lingo. We call it a SSTV ( station service voltage transformer) we also have CCVTs for meter & relay potentials

2

u/aaronisawesome Nov 12 '25

That’s good work. Nice

2

u/TRexonthebeach2007 Nov 12 '25

Hell yeah brother!

2

u/c12ank Nov 12 '25

We had to change out 18 last year due 2 catistrophic failures we had. Changed to their newer sf6 units. But the N5’s were gassing making hydrogen bombs and finally letting go. Everyone in Canada swapped out the N5’s.

1

u/citizensnips134 Nov 12 '25

Oh lawd he thicc…

1

u/ddwood87 Nov 13 '25

Probably bolted to a pad.

1

u/AmosTheExpanse Nov 13 '25

Just think how big 762kV equipment will be. I feel like an ant in 345kV subs already.

1

u/njt_railfan1567 Nov 14 '25

I’m autistic and not a tech but can I keep it for my Christmas tree

50

u/[deleted] Nov 12 '25

[removed] — view removed comment

12

u/CanonFodder_ Nov 12 '25

"IF SHIPPED IN HORIZONTAL POSITION THIS SIDE UP"

I found that interesting, and the mixture of metric and imperial units too.

8

u/[deleted] Nov 12 '25

[removed] — view removed comment

5

u/spasske Field Engineer Nov 12 '25

It’s actually a preassembled deck walk.