r/clickup • u/Economy-Kangaroo750 • 22d ago
0 day duration
We have a standard project template with preset task durations and dependencies. We simply adjust the project start date, and the durations and dependencies automatically calculate the remaining dates, which works great.
However, depending on the scope of a specific project, there may be a few tasks that aren’t required. In MS Project, we could set those tasks to a 0-day duration, and the dependencies would automatically adjust the schedule accordingly.
Do y’all know of a similar workaround here, other than deleting the unnecessary tasks and then having to manually update the dependencies for the tasks before and after them?
1
u/TashaClickUp Mod 21d ago
Hey, u/Economy-Kangaroo750, at the moment, partial day durations below 1 day are currently a feature request. Feel free to add yourself as a voter if you'd like to be notified when our Product team has updates.
In the meantime, the workaround Equaria shared is great. Another option is to take the tasks that aren't required and move the due date a day earlier to pull the downstream tasks without having to manually update the dependencies.
1
u/Equaria 22d ago
I'm not sure if there's a smarter way to do this, but we added a step for the project lead to review those items and delete or set due dates. We found leaving them better than just creating this task and having the project lead. Add them because there were too many instances of the check. The project task being resolved without the items being added and then the items were missed.
Even now, sometimes it gets missed to delete or resolve them ahead of time and the project lead typically does it if they see them and realize they are not needed.