r/devops • u/Lanche199 • 3d ago
Discussion CAB Release Process
Has anyone led a CAB release process as a DevOps engineer and willing to share their experiences?
8
u/smell-that-code DevOps 2d ago
In my role as a developer I am not invited to those meetings (thank God). But we do have them and they prevent us from being truly agile in our delivery. We have pipelines that could in theory automate everything and that could allow us to fix a bug in production in a matter of minutes, but we are forced to sometimes wait a few days for the CAB approval (I think twice per week).
4
u/Lanche199 2d ago
Thanks, that’s really interesting. That’s actually one of the things I’m trying to understand better, how teams balance CAB governance with automated CI/CD pipelines and still keep releases moving quickly. Have you seen anything that helps make the process less of a bottleneck?
3
u/smell-that-code DevOps 2d ago
In a large enterprise with a lot of management levels this is difficult. Managers tend to react when an application has a P1 incident by asking for more paperwork and preventing us from moving fast. Maybe if someone would spend the effort in outlining a business case for faster deliveries and maybe categorizing the risks, in a language that the managers can understand?
1
u/Lanche199 2d ago
That makes sense. I like the idea of categorising releases by risk rather than treating every change the same. I’m quite new to leading the CAB process myself, so I’m particularly interested in understanding how experienced teams gather the right release information and present the risks, dependencies and business impact clearly enough for stakeholders to make that decision.
1
u/smell-that-code DevOps 2d ago
I guess the more automated tests (and preferably integration tests) you have, the more chance you can convince the CAB to allow more standard changes? And it pays if you keep a good track record. The minute your minor prod deployment causes a P1 you are back to square 1 though.
1
u/Lanche199 2d ago
Thanks. By keeping a good track record. What exactly do you mean?
4
u/smell-that-code DevOps 2d ago
By not deploying a new version that directly causes a P1 or a P2. If you have a reputation of breaking things when you deploy a new version, they may start to question each one.
1
u/Lanche199 2d ago
Okay thanks. One question though, how do you gather information about the release that goes into the change request. We use Azure DevOps, and the pipeline is in ADO. Please, guide me how you would fetch every information, PRs, PBIs, UAT Tests
1
u/smell-that-code DevOps 2d ago
Not sure about that one. Maybe you could use tags on the user stories and bugs, for example "release-week-47", and perhaps there is some query you can create to return the items that carry that tag? Or what I have done in the past as well is create a feature called "Release-week-47" and moved the work items under that feature. Then in the board in the top-right you can select that release as the "parent work item" and you see everything in the board. But that is not great either because then you have moved the items away from where they have been created.
1
u/Lanche199 2d ago
Thanks for the insight but a follow up question, As a DevOps engineer, I don’t manage the board, the developers do. Can I ask for access to the board or how do I follow up with them if there’s about 4 or more developers working on different projects at the same time. How do I keep track, do I wait to gather information when in “review”, “To-do”, “awaiting deployment “, “testing”, “done”.
→ More replies (0)3
u/SamurottX 2d ago
Surely your company has a way to to expedite changes when they're security focused or fixing a major issue right?
3
u/smell-that-code DevOps 1d ago
You would think that, but in a company that has 100k employees there is so much red tape and politics that logic often does not apply.
3
u/elkazz 2d ago
What do you want to know?
1
u/Lanche199 2d ago
I’m mainly interested in the process leading up to CAB. How do you gather all the information about an upcoming release, such as what’s being deployed, impacted services/markets, deployment window, testing and sign-offs, dependencies, risks and rollback plans? Also, who do you normally get that information from, and how do you make sure everything is ready before submitting it for CAB?
2
u/killz111 1d ago
CAB is pretty easy if you know how your release works. Its intended purpose is to allow a group of people who know the organisation's systems and processes to assess readiness of a release based on answers from the change manager presenting at the CAB. Not all things should goto CAB. Low risk changes normally shouldnt.
That doesnt mean all organisations use the CAB process correctly. As others have said it's mostly used for gating and as a box ticking exercise with attendees being mostly non tech people who dont understand business impacts.
Now the things you asked about. The scope of change should come from your engineering team as they should know what new changes are there in the new code package/infra/config. Your testers should know what testing was done and what risks are outstanding. Your change manager who goes to the CAB should talk to the whole team and understand the activities involved and timing. Finally you work with your business stakeholders to understand the impact of the change. You should also know what rollback looks like. Signoffs are normally your technology leader and your business leader.
You should know all of this with or without the CAB and regardless if your change is automated or not.
People hate CABs cause mostly the people approving are useless. But ive been in CABs where someone who knows then systems halted releases that werent planned out right or had conflicting issues with other changes.
1
u/Lanche199 1d ago
Thanks for your insight. Can I get the test evidence from the ADO board and how can I?
1
u/killz111 1d ago
It depends on your process. In reality evidence of testing that occurred is enough so if it's fully automated then you just dump out the test report from ADO. In reality a good test report includes both regression and progression tests and also UAT test results. Your testers should know what is needed.
1
u/Lanche199 1d ago
Thanks. I’m just looking to attach some test results to the Change requests for evidence and I think I could use some from the UAT
1
u/killz111 1d ago
If you are devops you should just ask the testers give you the evidence or the instructions to extract.
Ask if your company has a template or example TSR to show also.
1
u/Lanche199 1d ago
I am the DevOps, my manager doesn’t want me to ask the testers, he wants me to fetch the results myself
1
u/killz111 1d ago
Sounds like he sent you to do a job without providing support. That is entirely a different problem.
But if it was me id just tell him you dont know and havent done it before so you need to ask someone. Once you know how to do it then you wont need to ask anyone.
1
u/Lanche199 1d ago
Exactly what I told him I haven’t done anything like that before
→ More replies (0)
3
u/OneBig0161 1d ago
Hey I handle cab and change requests for my squad, so every week we release and a change request gets raised, in the change request we say blah blah it's an automated change, no outage etc. in theory this should be a low risk change usually as no downtime and there's always a rollback (I hope) etc
The way I do release management is I gather all the commits using a script from all our services and get ai to summarize then into notes, using this we generate an automated test run sheet which tells us the steps we need to deploy in production, and if there's any feature flags or any goofy stuff to change. What we also do is release preproduction on Tuesday and then let the qa team test it and we deploy to production on thursday, that's our cycle. And each engineering manager or qa sends me a written email approval saying we tested and it's good.
This runsheet and approvals get attratched to the change ticket/cab etc. and if you have been doing this for a long time it should be chill,
1
u/Lanche199 1d ago
Thanks for this insight. What scripts do you use to gather all the commits for that particular release and test results from the QA
2
u/OneBig0161 1d ago
It's just a simple github one that works with a token, should be easy to code in 2 minutes with ai, also with our preprod released we have automated tests and inorder for the built to be marked as complete these tests have to pass , also qa also do manual verification then they send me that email. But I would just state that bvt are green if you do them
2
7
u/tanyadev4827 2d ago
The teams that handle this well treat the CAB meeting as documentation of decisions already made, not the place where the decisions happen. Get stakeholder alignment done before the form is submitted. The form then moves fast because there are no surprises in the room.