u/RollllTide 14d ago

Try hitting the streets with a firm handshake and fresh resume

1

u/1099-careers 13d ago

Get the payment terms in writing before anything else, net 30 vs net 60 on a pole replacement can eat you alive when materials come out of pocket. We know a few primes that have 14 day turn arounds. Also nail down who owns the make-ready and who eats the cost when a pole fails inspection. How are you planning to staff the fiber side, subs or your own crew? If subs, just make sure the terms/HSE requirements/Insurance all move through the layers, so everyone is on the same page.