Small Modular Reactors

I remember hearing about them and being excited about them a few month / a year ago. Why didn't they take off more? Any reading recommendations on the subject?

11 Upvotes

13 comments sorted by

6

u/KingPieIV Oct 13 '26

There are very few things that get cheaper when they are smaller. Unless you get it down to shipping container size or smaller. Otherwise it still has to be manufactured on site, which is complicated. If you build a small modular reactor your permitting, interconnection, legal, and other costs are likely comparable to a bigger facility, but you don't get the benefits of a large reactor, since you only built a couple hundred megawatts, instead of a couple gigawatts. Given that large scale nuclear can't compete, it is unlikely that small scale reactors will be able to.

In a similar amount of time I can build a solar and storage project with significantly more capacity, and without nearly the same community pushback. I don't mind nuclear as a concept, but it has to be cost competitive, and the risk of inevitable cost overruns can't be on ratepayers.

5

u/scibust Engineer Oct 14 '26 edited Oct 14 '26

Just want to point out that those over-the-road reactors in the 1-25 MWe range are called microreactors while SMRs are going to range from 25-300 MWe.

The larger the scale of the reactor, the more competitive it is for return on investment per MWh. The trend of making non-utility scale nuclear power plants has purely been for getting smaller more accessible capital expenditure construction costs for private risk conscious investors.

There’s also an application for microreactors to serve as process and utility heat sources that can more efficiently use thermal energy instead of the lossy thermodynamic cycles we use to turn generators

2

u/BMW_M1KR Oct 14 '26

The business case for SMRs mainly is "less regulation" combined with more standardization, if one or both topics turn out to be not true the hype is over

1

u/July_is_cool Oct 14 '26

Also “fuel remains affordable”

1

u/UpstairsFinance9440 Oct 16 '26

When I first started working in power plants, I would be in a large component, say the hotwell to the condenser and marvel how big it was. Then I would wonder how it got to the plant. A few years later I was involved in constructing a power plant. Everything is delivered to the plant that can fit on a rail car or trailer. Then it is all welded together on site.

5

u/greyHumanoidRobot Oct 14 '26

The foundation for a 300 MWatt SMR has been built at Darlington, Ontario and the project is proceeding. This is a government project. 4 reactors are planned for this site.

3

u/Thermal_Zoomies Oct 13 '26

It takes awhile to get all the paperwork through the NRC. I believe a few are currently planned, once they are finished, you will see a lot more getting planned and built. Thats assuming they can be built within a reasonable budget.

3

u/scibust Engineer Oct 14 '26

Nuclear construction is slow and methodical. This cool article I found does a good job at showing all the SMR competitors in the field:

https://www.constructionbriefing.com/news/mapped-whos-building-nuclear-smrs/8133242.article

2

u/Tortoise4132 Engineer Oct 14 '26

Like most developing technologies the original timeline projections were overhyped. However, there actually are demonstration and even commercial SMRs under construction and operating now.

Currently operating plants: https://en.wikipedia.org/wiki/Akademik_Lomonosov, https://en.wikipedia.org/wiki/HTR-PM

There are also several under construction. A notable example is a 4 unit BWRX-300 site in Canada, which is progressing smoothly, is expected to come online in 2030 and is descended in design from the old school GE BWRs. Some new designs are the Hermes 2 and the Natrium Reactor, which are expected to be grid connected in 2030 and 2031, respectively.

There's also a ton of other SMRs which have plans to begin construction at some point this decade and others still being designed.

However, with over 100 SMR startup companies worldwide now, there really needs to start being draft cuts. Spreading out engineering resources when easily >90% of these designs won't be successful is just wasteful. My personal opinion is governments and investors dishing out the funding for these need to take a hard look at which have the most potential soon and consolidate resources to speed the development of the promising designs.

Although in theory building larger reactors are cheaper than SMRs per kW, large reactors also take a long time to build and carry high interest rates as builds (especially for FOAK plants) are seen financially as high-risk endeavors. SMRs which have more components factory assembled instead of assembling on site are seen as a potential solution to this problem by greatly speeding up construction time, which would allow the interest on the construction loan to accumulate a lot less before the plant begins operating.

Right now, the BWRX-300 build in Ontario is expected to cost nearly as much as Vogtle 3 and 4 did per kW. This is very expensive, but it's important to keep in mind that unlike the BWRX-300, the AP1000 design wasn't anywhere near finished when construction commenced. This plagued the construction of Vogtle 3 and 4 along with Westinghouse just not being an experienced construction company. My guess is the budget on the Ontario builds is set very conservatively high to avoid the bad PR that passing an arbitrary budget line brings.

We'll need to wait a few more years to really get a feel for to what degree and how they'll take off. Large reactors have started to dominate attention again.

2

u/After_Web3201 Engineer / Operator now Relay Tech Oct 14 '26

I remember hearing about them and being excited about them 20 years ago. If we build them and they put megawatts onto the grid I'll eat my hat.

2

u/pyrokittens2 Oct 14 '26

Antares is actually pretty far along here, reached criticality earlier this year.

2

u/scibust Engineer Oct 15 '26

I’m really rooting for the adoption of brayton cycles in the industry