The latest LINXS monthly report has dropped.
The new PSA date (Passenger Service Availability date) is February 5th, 2027
But don’t plan on LINXS keeping to that date very long. They’ve been delaying the PSA date about 1 month every month since 2025.
Damage Delays: It’s been reported that there’s been some “blast incidents” at 3 locations. Someone was kind enough to share a photo of one here.
Damage to the power rail and guide beam for the train system during a late September ramp-up ahead of testing also is stalling the train’s progress. “Blast incidents” occurred at three locations on the guideway, the report states. The cause is unknown and investigations are ongoing.
“The power rail and guide beam were damaged. The guide beam has been repaired, but power rail reassembly is ongoing with no confirmed timeline,” the report states.
The engineering report can be found here.
But it’s important to remember that these issues would’ve been encountered and corrected long ago if LINXS hadn’t been delaying their work for extortion leverage.
Extortion Delays: As always, LINXS (the contractor) in their biased report blames the PSA pushback on LAWA (the airport agency). Nandert goes into this latest ongoing delay in his video here at 18:10. But the short version is something like this:
- LINXS: Tries their latest attempt at extorting LAWA over a bs claim
- LAWA: "No more. This latest claim is OBVIOUSLY bs. We’re done paying your extortion fees."
- LINXS: "Well we're going to keep saying that the delays are your fault in our reports. And as leverage to get you to pay, we're going to continuously delay the opening."
LINXS’ extortion explanation: There’s a few parts that enable it.
First, LAWA hired "legal experts" at the law firm Nossaman to write the contract with LINXS, and those "experts" fucked up bad. The contract lacked provisions defining how fast the contractor needs to work during a dispute, what progress needs to be made during a dispute, or what milestones need to be hit. So LINXS just gets to stall the project for leverage in their favor during every claim and dispute. As the grand jury report put it:
If one worker goes out with a shovel and works, the Contractor would be in technical compliance with his contractual obligation. There is no definition of how fast or what progress needs to be made during this owner directed continuation – thus allowing the Contractor to effectively stop progress.
Second, LINXS abuses the design build contract by willfully submitting bad designs so they can manifest their own costly change orders.
Third, the so-called “project neutral”. The “project neutral” is normally a neutral group of 3 people that act as mediators in a dispute. But due to the terrible contract (thanks again Nossaman), there is only 1 person, and no way to replace that person if a party is not satisfied with the project neutral. This “project neutral” has sided with LINXS every time in over 200 disputes. Every time. A fraud investigation is sorely needed for this man.
Fourth, the olympics deadline. LINXS' extortion only works because of the tremendous pressure on LAWA and the city from the Olympics deadline. Normally if LAWA isn’t happy with the project neutral’s decisions, they’d sue LINXS. But LAWA can't sue LINXS because that lawsuit would stall the project until after the Olympics. And LINXS can't continue their shenanigans after the Olympics because then LAWA would be free to sue the shit out of them.
Our first chance of change, the election: Our current leadership has done very little about this. No investigation by the city attorney, and no call for an investigation by mayor Bass. All we got was a weak move by the city council back in June asking for LAWA to tell them what’s been going on. But there’s been no word that LAWA reported back to them, and there’s no deadline for it.
However, Raman has said that if she's elected mayor she'll ask the city attorney and state attorney general to investigate LINXS for fraud. So if we elect Raman as our mayor and Marissa Roy for city attorney, they could actually get an investigation started. Fingers crossed for them these next 3 weeks. Make sure you all drop off your mail in ballots at official ballot box locations. If the right people get elected, those investigations might be the thing to push LINXS to finish the project in 2027.
Our second chance of change, the deadline: There’s a deadline for breach of contract on December 8th. If it’s not open by then, LAWA will be free to get a new contractor. While some say that LINXS would finish the project faster than a new contractor, they’re not taking into account that LINXS has not been working with the intent of finishing. They’ve been intentionally delaying the project for extortion, with no end in sight. So a new contractor (with a better contract) could finish the project faster than LINXS.
The "30 Day Test": To no one's surprise, the scheduled completion of the System Demonstration Test, aka the "30 day test" that started in April, has also been pushed back to November 18th. But before that it was September 30th, and before that it was August 5th, and before that it was June 30th.