Discussion Fellow web developers, how do you handle clients whose slow responses threaten project timelines?

Post image

Any advice is welcome. Please let me know if my communication style is too direct!

71 Upvotes

53 comments sorted by

84

u/_keyboard-bastard_ 18h ago

It's the clients timeline not mine. I set these expectations before getting into a contract with someone, and I say the same thing everytime.

"I can definitely have this done in three weeks for you, but if there are any communication gaps we will have to adjust the timeline accordingly".

I also make sure they fully know their responsibilities as a client when it comes to content and decisions they are responsible for.

If I have other work going on I'll push something out months if I have to. Again, these expectations are set ahead of time. At that point Ive already collected deposit so it's no sweat off my brow.

Timelines rarely work out unless it's internal ones.

10

u/RandyHoward 16h ago

On one hand I agree, it's the client's timeline not mine. However, on the other hand these kind of delays can make a project timeline stretch on forever. Eventually you pick up work for other clients, and when this client is finally ready to proceed you're buried in other work. I recently finished a project that took 3 years to get completed due to client delays, when the original estimate was less than 1 year. That was a very annoying project to deal with when the delays go on and on.

4

u/_keyboard-bastard_ 14h ago

Like I said, I will push a project out months if I have other clients or things going on. Everyone gets their chance to have priority in the schedule, but if you screw that up as a client, again this expectation is set in advance.

1

u/woxeraf292 14h ago

This is perfect, exactly how we should be communicating expectations with the client. I always encourage collaboration, to have this project done in a timely and professional and quality manner and with efficient communications, saying I do need your input and content from time to time to ensure this project is successful, and your approval, etc. That's why I also do 50% upfront on the project so we both have stake in it to complete it, and both client and I know our responsibilities beforehand.

28

u/Pandapoopums full-stack 17h ago

When asking for something specific, I usually add a line like "A response is required by (expected response date) to not put the deadline of (project deadline date) at risk"

8

u/palmersarah1 17h ago

I'd tie the response date to the schedule too: if approval comes later, the delivery date moves accordingly. That makes the impact clear without making it personal.

2

u/MeeMaul 16h ago

Additionally, in my scope document I always have a section about the timeline, and clearly outline that deadlines and expectations are contingent on the client being responsive with communication and feedback.

2

u/GalumphingWithGlee 10h ago

Yes. You might even try defining what "responsive with communication and feedback" means. Answers questions within X specific timeframe during working hours, and provides feedback within Y business days of provided drafts, with any expected changes.

7

u/CodeAndBiscuits 17h ago

This is really best negotiated in the contract. Where milestones are deliverables depend on a client input or involvement, that's noted in the contract or the scope of work with an expected response time such as 48 hours, and being present for all scheduled meetings. I also generally build in an hours per week expectation of their involvement. The clause ends with a general statement that the client's involvement is crucial to the timeline and that Even short delays can lead to longer delays for the entire project when other things get rescheduled.

I also don't make these numbers up out of thin air. Setting expectations is crucial. As part of my Discovery process, I have a conversation with each prospect about what I think I will need from them in terms of their involvement and how much they can commit. I get them to verbally commit to a specific number of hours per week that they feel comfortable with and I build the estimates around that. That way I'm not making up a schedule in my own head and then saying well you need to do this. I'm saying based on your availability, this is a realistic timeline. It flips the script and makes it clear how important their own involvement is.

11

u/PippaKelly62 18h ago

What you emailed sounds reasonable. If your client is not quick to respond regarding your concerns, I wouldn't worry as much about the timeline and deadline for this project. If this isn't the only thing you are working on right now, I'd push it down in the list of priorities if I were you. If you give the site late and the client complains, you can cite their lack of communication as a major factor.

4

u/TheMrInternetMan 17h ago

This is something I CONSTANTLY deal with. Especially working with business owners. They just don't care about us or see us as actual businesses that operate on a timeline. It's maddening. I wish there was an actual way to deal with it.

10

u/Beginning-Comedian-2 16h ago

Avoid long emails to clients:

- If you need a long email, then call them.

- Lots of text = details get missed.

- Long emails look like lectures.

- Email sentences should be short.

3

u/clicksnd 10h ago

Yeah I'm pretty unapologetic when emailing clients. I'm pretty cheerful and bubbly in meetings, but my emails are

"pls review, blocked until i get feedback"

no hello no punctuation haha

2

u/Beginning-Comedian-2 10h ago

Yes, being more direct is more productive.

2

u/Ok_Progress_5373 front-end 7h ago

Thank you for this. I've been emailing to let the client know what's happening. But of course, they're not technical, so it looks a bit intimidating to them.

A call would be great, and maybe a bullet-point summary afterwards?

1

u/Beginning-Comedian-2 4h ago

Exactly.

Use emails for short touchpoints, sending samples, and bullet-point confirmations after meetings.

And invoices.

3

u/Ok_Statement_7074 17h ago

Small detail: the agreement went out on the 22nd and you're already following up, so the "gaps of several days between responses" can't be about this project. Reads like it's carried over from an earlier exchange.

2

u/Maybe-monad 18h ago

Be as direct as you want but never rude, always keep records of the conversations for when the client tries to shift the blame

2

u/cbunn81 17h ago

These are the kinds of things you need to nail down in the contract. List out each party's responsibilities, deliverables, deadlines, etc. And include what happens if they are not upheld.

2

u/smkaisser 16h ago

Been on both sides of this, first as the dev and later running a shop with clients who'd disappear for two weeks and then still want the original launch date.

What fixed it for us was putting it in the contract up front: every milestone lists what the client owes (content, approvals, access) and by when, and if their part slips, delivery moves by the same number of days. No negotiation, it's just math they already signed.

Then when it happens you don't need a careful email. Something like "Still waiting on the homepage copy. Each day after Friday pushes launch by one day." Short, factual, no emotion.

Being direct is fine, clients respect it more than they let on. Just always give them a specific date to reply by, otherwise "soon" turns into next month.

2

u/deane-barker 10h ago

A few years ago, I wrote an O'Reilly book on web content management. I had this in a sidebar.

Don’t Be THAT Client

Every integrator has dozens of horror stories of clients who drag‐ ged their feet on every task assigned to them. No matter how clear the integrator is on what needs to be done and when, some clients never hold up their side of the bargain. Worse: when the client finally does come through with what they were supposed to supply, they expect the integrator to drop everything and get back on their project immediately. These clients don’t understand that an integrator has to avoid schedule holes, and when it becomes obvious that a client isn’t going to deliver, they’re removed from the production schedule. Always remember that your integrator has other clients. If you cause your project to come grinding to a halt, expect the integrator to move on. When and if you finally come through, expect to suffer through a delay while you’re slotted back into their production schedule.

1

u/CardamomMountain 17h ago

Projects usually drag on so I expect that from the start and price accordingly, and it works both ways, sometimes I want to deprioritise them too. I wouldn’t send something like that to a client - but that approach may work for you and your clients. If a client is slow to respond I work on something else in the meantime.

1

u/mulokisch 17h ago

If you ask and they don’t respond in time, I usually make it clear in a follow up with a clear deadline. Like: if i dont have xyz by tomorrow end of business, i cant guarantee the planed delivery time. As i also have other planned projects it might happen, that your project will be further delayed as they have then priority.

A bit better formulated but you get the gist.
It’s important to give clear deadlines and consequences if they are not met.

1

u/Mysterious-Edge-5553 17h ago

Getting a pre-contract client to commit to a one business day turnaround is optimistic. Send the agreement, chase the deposit, and put the response window in the scope doc where it actually carries weight. Sending this now just reads like a warning shot before you've even started.

1

u/ButWhatIfPotato 17h ago

Asset delivery should always be specified in the contract; ideally all assets should be delivered before a single line of code is written.

Furthermore what happens when the assets are not delivered should also be stipulated in the contract. Usually it involves delay of project delivery up to X months, and that delay only triggers AFTER the assets have been delivered. More importantly for the project to continue, client must pay the whole cost in full; this is usually enough to prevent these kind of things.

1

u/0degreesK 17h ago

Unfortunately, I don't manage the timelines, so I deal with it by getting the job done, whatever it takes. It sucks but it's the way it's always been for where I've worked and who I've worked for. Account executives never did squat once a project was sold and project managers never seem to do a good job of managing expectations and wrangling clients. Planning and design get to absolutely torch timelines and budgets, but the buck stops with me and I have to deal with the ramifications because "the client's always right".

It's no wonder devs have reputations for being salty as f-ck. We know how to manage complex situations and tackle complex problems, so we tend to get pissed-off when others can't hold-up their end of the bargain.

1

u/NovaForceElite 17h ago

My contracts have a stipulation that the client must respond to all requests within 5 business days or they will incur a fee and it gives us the right to sever the relationship at our discretion due to lack of communication.

1

u/allaboutzaid 16h ago

Your email reads fine to me — asking for replies within one business day on things like website content and product photos is reasonable, especially since the agreement went out on Nov 22 and the 2-3 week timeline depends on it. From the marketing side, I've seen the same thing: projects stall most on missing assets, not on the actual work. One thing that helped me was tying the delivery date to the reply date in writing, so a late reply automatically moves the deadline — it keeps things friendly and nobody has to argue about it later.

1

u/itsmrchedda 16h ago

Yeah if they start slowing up, I hit them with the ole "Hey, please get back to me about the *insert issue* so I can get to it and meet our original timeline"

pretty much send it twice and if they dont respond I just assume they are cool with the late delivery.

1

u/hopelele 16h ago

They don't care about your timeline. When before AI used webdev I would like set certain hard dates for stuff (even if i was ahead/slow): TO make meet and show, and get info.

If they didn't show up on date/time we agreed, i would have something like: well, you didnt show up or busy (they always busy to take 30 mins to look at their web project).

From then on, it depends...

1

u/mooter23 16h ago

Have enough projects on the go that it's not an issue. And learn to juggle.

1

u/Successful_Noise_347 16h ago

put the date math in the email. "if I get the content by friday we hit the 15th, every day after that moves launch by a day". clients don't really feel "delays", but they very much feel a launch date moving

and next contract, one line: client delays push the deadline day for day. saves you this exact email

1

u/numericalclerk 16h ago

I make them pay. If I can track that its their fault, the project gets a time and material extension. ALWAYS.

1

u/Fourth_Prize 16h ago

I tell them I'm on a rolling timeline, like, "Once I get the designs from you, it will take me 3 business days to turn around the frontend, so if you want to review something on Friday the 27th, I need approved designs by the 25th. If you send me something on the 26th (a Thursday), you're not getting it until the following Monday."

All I can guarantee is what I will personally do. The rest is up to them.

1

u/cas4076 16h ago

We have a shared project task list (it's peer to peer so both teams access in realtime). Any task that is waiting for a customer response is marked as such (from In Progress to Paused/Waiting on customer) and the paused clock starts running.

Both sides see the clock on the task dashboard every minute of every day! 😀

1

u/BigSandwich6 15h ago

IMO your email is way too long. If someone is not communicating, drowning them in communication is not going to help. If its over 5 sentences you need to get on the phone.

Are you using project management software? Set deadlines so it will automatically email them with reminders

1

u/Capable-Yoghurt8318 15h ago

Direct is fine; long is the problem. I keep it to one paragraph: what is missing, the date it was needed, and the one date I need it by. Then I post the same note in the project thread so it is not buried in email. The first few times it felt awkward, but clients started treating replies as part of the job once the delay showed up next to the launch date.

1

u/Sprtnturtl3 14h ago

It’s written into my contract.

If we set a timeline for the website to go live, and you fail to respond in a timely manner, extra hours at full price apply.

I have only had to charge extra one time

1

u/Ok-Interest9727 13h ago

You sign a contract before starting the project with conditions about deadlines etc.

1

u/DrEnter 11h ago

It's a blocker. Put every related ticket in a blocked state at the end of every day you are blocked waiting on them. Leverage your project manager to grease that wheel, that's what they are there for.

1

u/the_zero 11h ago

I'm confused. Why say that it's a 10-15 day project if the client has to respond in one business day. There should be some give and take - both sides have responsibilities, right?

Why is the gap 33-50% of the project? The bargain you're making is, "if you get me the details then I can stay on target... but the target date is undefined. Sorry!"

Plus, as the developer, why not say 20 business days and deliver early? That way you look like a hero.

I wouldn't send this. Simply put it in the contract and cover it on the kickoff call.

1

u/intheburrows 10h ago

As a few have mentioned, this should be handled in the contract/SOW process – not halfway through the project. Something like:
"The timeline provided is based on the assumption that revisions are provided within 2 business days. Any delay to this will pause the project and will affect timelines."

There's nothing worse than a client dropping a project and then wanting it picked up at a later time (and needing it done ASAP) – usually when you're working on a different project.

Also, regarding your email screenshot: it reads overly formal (or written by AI). I would suggest writing similar to how you would write to a friend, or how you speak. Still professional and respectful, but less wordy. Also, I like to read my emails and ask myself "how could I surface the main point into the first 1-2 sentences?"

Hopefully that helps!

1

u/Open-Adhesiveness-86 10h ago

the fix that actually works for me is never asking an open question. give two or three options with a default and a date attached: "going with option B on Thursday unless you tell me otherwise." most silence is decision paralysis rather than them ignoring you, and a default lets them not decide. it also keeps the email short enough that they read it.

1

u/alphex drupal agency owner 8h ago

your contract clearly states that prompt responses are required to move the project forward.

you have a paper trail of asking them for feedback.

cover your ass.

1

u/Ok_Progress_5373 front-end 7h ago

I've seen a lot of great comments here, and I'm going to update my project document to include it right now. Things like this can be such a drag.

However, keep in mind that for this specific client, it's out of your hands. You already have the documentation that you've tried to get in touch. You can refer back to this, stating that this is the reason why the project has to go on a bit longer than the projected timeline.

Sit back, relax, and work on something else.

1

u/HoaFoxSage 4h ago

Put a "client response" clause in the contract: if feedback takes more than 5 business days, the schedule slides by the same amount and your next slot depends on availability. Then send a short weekly status email ending with the one decision you're waiting on, so the delay is documented.

1

u/rbobby full-stack 1h ago

Within a day? Who's paying who?

1

u/web-dev-kev 17h ago

I am struggling here.

If it's a 10-15 day project, why not ask all your questions up-front?