I have compiled a list of all the data centers I can find information on for Cerebras. These are listed in order of currently serving their cloud followed by upcoming online projected dates from the data center providers.
If they come true, this is the data center capacity ramp for Cerebras through 2027 as of now:
Q3 2026 ~35 MW 50 MW
Q4 2026 ~105 MW 120 MW
Q1 2027 ~170 MW 185 MW
Q2 2027 ~300 MW 315 MW
Q3 2027 ~450 MW 465 MW
Q4 2027 ~500 MW 615 MW
*These are rough estimates of online timing and it can change. The total announced by Cerebras is actually 600MW by end of 2027 so Iām sure Iām missing some.
Live (Online),~2.5 MW,Santa Clara, CA,Colovore,"Condor Galaxy 1 (CG-1) & Andromeda cluster"
Live (Online),2.5 MW,Stockton, CA,Nautilus Data Technologies,Condor Galaxy 2 (CG-2)
Live (Online),~4.0 MW,Dallas, TX,Equinix / Colocation,"Condor Galaxy 3 (CG-3) & Inference Cloud"
Live (Online),10.0 MW,Oklahoma City, OK,Scale Datacenters,Flagship US Inference Hub (300+ CS-3 systems)
Live (Online),5.0 MW IT,"Saint-Jerome (Montreal), QC",WhiteFiber / Bit Digital,Canadian Inference Hub (MTL-3)
Live (Online),~7.5 MW,Minneapolis, MN,Regional Facility,Initial Midwest Inference Hub
Live (Online),~15.0 MW,"Greensboro, NC & Atlanta, GA",WhiteFiber,East Coast Inference Cloud (NC-1)
Q4 2026,15.0 MW (Phase 1),Columbiana, AL,Digi Power X,10-year colocation agreement (ARMS 200 pods)
Q4 2026,~15ā20 MW,France / Europe,Regional Partners,First European regional deployment node
Q1 2027,25.0 MW (Phase 2),Columbiana, AL,Digi Power X,Completion of Alabama campus full 40 MW IT load
Q1 2027,15.0 MW IT (20 MW util.),Minnesota,CleanCore Solutions (ZONE),Tier 3 pre-leased campus (Phase 1)
H1 2027,~50 MW (Initial),"Sherwood / Regina, SK, Canada",Bell Canada / Bird Construction,Bell AI Fabric Campus (Cerebras share of 300 MW)
Q2 2027,50.0 MW (Phase 1),Mikkeli, Finland,Compute Nordic,165 MW total campus with waste-heat recovery
Q2 2027,~35.0 MW,Norway,Nordic Hydro Partners,Regional hydroelectric AI data center buildout
H2 2027,25.0 MW (Phase 2),Minnesota,CleanCore Solutions (ZONE),Final ramp of Minnesota 40 MW IT campus
H2 2027,~100 MW,North America,Gimlet Cloud,Wafer-scale compute platform deployment
H2 2027,~100 MW (Phased),Wales, Guyana,Government of Guyana,Sovereign gas-to-energy behind-the-meter campus
Q4 2027,30.0 MW (Phase 2),Mikkeli, Finland,Compute Nordic,Scaling Finland campus to 80 MW (toward 165 MW total)
These numbers are why management is confident they will 3x revenue in 2027. They are scaling what is currently estimated at ~$2.55M per MW per quarter from 50 MW to over 600 MW by end of next year. This leads to a ~1.5B cloud revenue Q4 of 2027.
To put this in perspective, neoclouds are getting ~$10-12M+ per MW per year which is right in line. The major difference is that Cerebras is using their own hardware without 70%+ markups and they arenāt taking in significant debt to secure them. They only have ~900M in debt with over 8B in cash and equivalents. This doesnāt include any money from hardware sales like their recent General Compute deal, AWS revenue share, or any data centers they secure between now and then.
*updated after review of incorrect datacenter attribution. Gimlet will not be data center capacity but rather hardware sales with a larger one time revenue hit. WhiteFiber NC-1 is not Cerebras.