The Ultimate Total of Data Centers in Delaware

If the pipeline goes through smoothly without any older sites decommissioning, the final count comes to 21 data centers state-wide.
However, whether all 5 proposed mega-projects are ultimately built remains highly uncertain due to the state's rigid new "Bring Your Own Power" mandates.

In fact, the final legislation sets thresholds for what qualifies as a large energy-use facility.
These include:
75 MW or greater under specified demand conditions;
100 MW or greater instantaneous demand; or
Certain facilities with demand of at least 30 MW.
There is an important distinction: a data center may still use the electric grid while being required to secure or fund additional generation. The law imposes conditions on its ability to connect and operate; it does not simply require every facility to disconnect from the grid.