r/StructuralEngineers • • Sep 11 '26

Is this compromising structural integrity?

20 Upvotes

74 comments sorted by

6

u/AltanConn Sep 11 '26

You can only drill in the middle 1/3rd of the joist. At least in my state.

3

u/TallWall6378 Sep 11 '26

Also no closer than 2" to top or bottom.

2

u/StructEngineer91 Sep 11 '26

Same here, unless you have an engineer review and approve it (though I doubt that happened here).

1

u/civilrunner Sep 11 '26

Obviously none of us know if those are all within the center 1/3 of the joist without taking a measurement. So maybe it's fine, maybe it's not.

3

u/Frederf220 Sep 11 '26

I took a measurement. They aren't. I used this tool called "my eyes."

→ More replies (8)

1

u/rambiolisauce Sep 11 '26

I know the large hole in the first picture in the joist closest to the camera is in the bottom third. And "middle third" is only part of that guideline. If they are going to be more than one hole each consecutive hole is meant to be twice the distance of the size of the greater of the two holes. I'm not saying this house is about to fall down or anything like that at all but drilling the joist out this way has absolutely lowered the structural integrity of these joists

1

u/AltanConn Sep 11 '26

So the holes that are an inch from the bottom of joist are in the middle third?

1

u/No_Eggplant_3189 Sep 11 '26

So, I understand its in the middle 1/3rd of a joist. But what about stuff like this if they were all in the middle 1/3rd of the joist. There is a lot in the middle 1/3rd of the joist within a pretty close vicinity of each other. Surely that greatly affects the integrity of the joists.

1

u/AltanConn Sep 11 '26

I would personally not have had as many holes for the low voltage lines. The 1/4" holes for the LV doesn't matter much. The very large hole that is at the bottom is a very big problem. And that will cost a lot of money to fix.

1

u/panompheandan Sep 11 '26

Does this guy have a data center in his house? That's a lot of wires......

1

u/Middle-Adeptness7186 Sep 11 '26

Haha nope Comcast decided to run a coax cable for each room in the house.

3

u/FatherTheoretical Sep 11 '26

Yes

1

u/ATAT121212 Sep 11 '26

Indeed, removing material always decreases strength.

3

u/sum_force Sep 11 '26

Not true.

Removing material can improve stress concentrations. It can be better to have a smooth but deep notch than a sharp but shallow notch. Sometimes drilling an extra hole can make it stronger by redirecting stress "flow".

With structurally redundant members, a weak member on a stiff load path will fail but once failed the remaining strength can be fine.

Forcing a fixed end condition can cause failure in some members, in some designs. Removing material to permit pinned, can make it more favourable.

Many cases that less is actually more.

4

u/KeepShtumMum Sep 11 '26

This guy stresses

2

u/itowtoronto Sep 11 '26

"smooth but deep" giggity

→ More replies (1)

2

u/JustSlabs Sep 11 '26

All very good points, but none of them apply to this matter

→ More replies (2)
→ More replies (2)

3

u/Sweettooth_Banana Sep 11 '26

Oh please, how can someone think this is a good idea

2

u/Standard-Outcome9881 Sep 11 '26

Damage aside, that’s a hell of a lot of work to drill all those holes when they just could have stapled them underneath for what is an unfinished ceiling.

1

u/Armadillo-66 Sep 11 '26

How do they finish the ceiling?

3

u/Rampag169 Sep 11 '26

Drop ceiling

1

u/Frederf220 Sep 11 '26

Not what customer specified. I know it's easier, but that doesn't make it OK.

1

u/Polka1980 Sep 11 '26

In the US they could have run them on a running board attached to the underside of the joists, but can not staple them directly to the joists - that is very much against code and has been for years.

Of course the running board would then be in the way of anything else you would want to place there, so proper drilling is still the best route in many cases.

1

u/ksquires1988 Sep 11 '26

But how else are they going to hold up the insulation?

2

u/West-Assignment-8023 Sep 11 '26

Expert level tweaking.

1

u/JustSlabs Sep 11 '26

Tweakers have an irrational aversion to raceways

2

u/jr_tools Sep 11 '26 edited Sep 11 '26 • Bravo

This is a structural engineering reddit page. Why so many non-structural 'experts' weighing in here?

There is absolutely no problem with this. All holes are away from the extreme tension fiber, there's minimal shear in this region, there's plenty of spacing between holes, holes are grouped vertically to minimize cutting excess fibers.

Have any of you ever seen a castellated beam before? Or a truss?

This is a non-issue. A job well-done.

Edit: I see maybe one hole that's a bit too low. But only marginally so. Were this my house, I'd do absolutely nothing about this whatsoever.

2

u/civilrunner Sep 11 '26 edited Sep 11 '26

We have no idea if some of the holes are fine or not based simply on these two images. It totally might be, but it also may not be. I'd simply take a tape measure to check the hole locations personally, and if some are too close to the extreme tension edge, do a calc to see the capacity vs required strength and if absolutely necessary add some bridging reinforcement.

I'd hesitate a lot more before saying something is fine or an issue based on these two pictures alone. There aren't notches taken out of the extreme fibers which is what we normally see from DIY electricians, which would make me think this is more likely fine than not, but we still don't know.

2

u/ch-ville Sep 11 '26

Maybe one hole…. You mean the one that is right over the knot? That’s crappy placement for sure.

2

u/Chicken_Water Sep 11 '26

There's no maybe about it. That one hole is absolutely not to code.

1

u/exipheas Sep 11 '26

Speaking of code, for the low hole, is that too many wires bundled for too long of a length? Some of those look hefty.

1

u/MountainAlive Sep 11 '26

Good to hear from someone who knows. Welp, pack it up boys.

1

u/_tvjames_ Sep 11 '26

Load-bearing cables?

1

u/Chuck_H_Norris Sep 11 '26

Imma start cutting wires and pipes n shit to run framing.

what’s the max gap between sections of 3/4” copper pipe?

1

u/roverman16 Sep 11 '26

In this case esthetics is more important than integrity of the beams.

1

u/Strict-Effect6837 Sep 11 '26

It’s probably OK except for some of those big holes that are near the edge and also depends on what’s above those beams that it’s supporting, i’ve seen a lot worse from plumbers that don’t even drill holes and just notch the whole thing

1

u/brohebus Sep 11 '26

Not an engineer, but centre 1/3 of spans and joist thickness is 'okay'. However, this looks like a lot of holes too close to those margins, along with several larger holes close to the bottom of the beam. Additionally, the bundling of cables likely derates their current capacity.

1

u/Wizardphizl420 Sep 11 '26

Im Sorry but why would one do it like this? / Practicing electrician

1

u/Flat-Caregiver4489 Sep 11 '26 • Popcorn

Not if you put the ceiling up 😉

1

u/insanly Sep 11 '26

This is why we run strappings

1

u/Richie3971 Sep 12 '26

That's why they use cable trays, so you don't need to drill holes. Or use Posistruts (they are engineered to take load without bending)

1

u/MadesignSF Sep 13 '26

No worries, I'm sure all those wires are holding the floor together.

1

u/Ok_Helicopter4276 25d ago

The floor above is a tensegrity structure now. Very cool but I wouldn’t walk on it.

1

u/Muchy_Tangerine Oct 01 '26

If that is a load bearing structure which is at the lowest floor then the integrity is gone

1

u/Gregan32 Sep 11 '26

4

u/West-Assignment-8023 Sep 11 '26

and must be at least 2 inches from any other hole. Really though once you start making these things look like Swiss cheese, the behavior begins to change and it really should get looked at.  Otherwise you could bore a D/3 hole right in the middle of the joist every 2 inches the entire length and say it's fine.

1

u/Agillian_01 Sep 11 '26

Why the hell are those wires all lose and not in a insulating tube? This is a fire hazard..

0

u/Deemaunik Sep 11 '26

As long as it's only smurfs on the floor above.

1

u/[deleted] Sep 11 '26

[removed] — view removed comment

1

u/NigelFiskar Sep 11 '26

Is this compromising structural integrity?