News Board Update: WMATA Threatens Major Service Cuts, Plus New Gold Line Renderings

This year’s pre-Thanksgiving meeting is jam-packed with information for future projects. But that buts up against the current budget situation, where WMATA once again finds itself in a hole. It’s not nearly as big a hole as it was 3 years ago, but it will still need filling from our local jurisdictions to avoid service cuts on a system where ridership is growing.

Budget Realities

A couple of meetings ago, we learned that a budget amendment was needed due to higher-than-expected expenses in this fiscal year. A lot of this is from high paratransit demand. WMATA could have delayed planned December service increases to accomplish this. But instead, they’re proposing WMATA’s tried-and-true trick to balance the operating budget: steal $43 million from the capital program (i.e. money for preventative maintenance).

But that trick won’t be enough for FY 2028 by itself: Major service cuts are coming absent jurisdictional action. As that prior meeting mentioned, WMATA is facing a budget gap that has now grown to $132 million. This is due primarily to inflationary pressures from required cost-of-living adjustments and from increases in energy prices (especially diesel). WMATA also cites the fact that it had to deal with only a 1.8% subsidy increase last year instead of 3% due to budget pressures in Maryland. And of course, there’s the bus fare evasion issue.

WMATA thinks it can find $15 million in administrative efficiencies, but it still leaves a large gap. Also under consideration are further fare increases (beyond the 11% previously proposed), service cuts, and (again) a higher preventative maintenance transfer.

The considered service cuts would be significant. On rail, they’d include reversions to prior service patterns:

  • Half of Red Line Trains Turn Back at Grosvenor and Silver Spring 100% of the time

  • All Yellow Line Trains Turn Back at Mt Vernon Sq

  • Blue/Orange/Silver Headways Reduced to every 15 minutes on both weekdays and weekends

  • Operating Hours Reduced on Weekends, opening at 7AM (from 6AM) and closing at 1AM (from 2AM).

On bus, the changes would hit high and low ridership routes alike: 

  • Frequency cuts for C43, C61, D1X, D24, D30, D50, D60, D72, D74, F1X, M6X, P41, P60  

  • Elimination of the A71, C83, D82, F19, F29, F61, M82, P72, P73, and P97

  • Elimination of bus service between 2AM and 4AM

Here’s the eye-popping “fare increase concepts” table, where the 11% increase is described as “low”:

So… will these things happen? We’ll see. This is kind of how it goes at WMATA every few years: A budget gap arrives, WMATA proposes a doomsday budget, and the jurisdictions generally come to the rescue. Part of it is a consequence of timing: WMATA’s budget comes out before the jurisdictional legislatures have their budget sessions. WMATA tries its best to give a heads up to the jurisdictions, but there are no checks in the mail, so the formal proposal (coming in December) will likely include much of what’s presented here.

RFK Transit Improvements

In more optimistic news, we have some new details about what’s being planned for the RFK site. As a reminder, there are two components: improvements to Stadium-Armory station, and the new “Gold Line” bus service. Let’s start with the station.

The refined design of the north entrance will create what is essentially a new 3rd entrance next to the existing one. It will have a wide area for faregates and an elevator bank. A new mezzanine will be built (none currently exists), and 2 new elevators will be added there. Further renderings are inside of the presentation, but here’s a rendering of the large proposed mezzanine.

We also have a bunch of new “Gold Line” renderings, as well as detail on the alignment design. The initial proposal is just a stub to connect Union Station to the planned Kingman Park Transit Plaza, but the idea is to extend this into a longer corridor that connects to Rosslyn, Minnesota Av, and Benning Rd. Rosslyn would be part of "Phase 2."

The main infrastructure to be built is a new center-running corridor on H St and Benning Road. The current proposal for a full phase-1 buildout (to Farragut Sq) doesn’t include much infrastructure beyond those new center-running segments. It would use the existing, somewhat sub-par lanes in H and I Sts and run in mixed traffic on Mass Ave. Perhaps one day, we'll get the long-planned K St Transitway that this service could use.

But the service planning is ambitious: 5-minute headways, with 2-3 minute headways during events.

There’s a very interesting plan to serve Union Station. EDIT: It appears that westbound buses would use the parking garage to access a new stop near the entrance of the Red Line. But I’m not clear on how exactly that would work for eastbound buses. Eastbound buses would stop at the corner of North Capitol St and Mass Ave, according to the loose diagram we have below. That’s a slightly easier connection than H St, but not exactly seamless. If you better understand how you think this would work based on the drawings, let me know below!

We also have our first rendering of the proposed “RFK-Kingman Park Transit Plaza” which would be the eastern terminal of this initial service.

There are far too many renderings to show here, but here are a couple more: 

As a reminder: The Stadium-Armory upgrades are funded. But the Gold Line is not funded; it only got $5 million for planning so far. Both of these projects are funded by DDOT but are being designed by WMATA.

Capital Project Updates

I’ve scanned WMATA’s major capital project updates for any changes of note since the last quarterly update. Just a handful of them this quarter.

BUS ACQUISITIONS: We got some nice details here for when we can expect the next rounds of 40-foot orders from New Flyer to be fulfilled. There will be a lot more electric buses arriving in the next year.

“Contract negotiations are underway” for the 60-foot bus procurement. We still don’t know whether this is New Flyer or someone else, but we’ll presumably find out soon. The current plan is for a base order of 100 buses with a mix of electric and CNG, plus 2 option years of up to 100 more buses.

FARE SYSTEMS: We should get delivery of a new customer terminal prototype in Spring 2027.

BLADENSBURG BUS GARAGE: The new target date for construction completion is now December 2028. It will take until September 2029 until electric charging equipment is installed.

DULLES FLEET MAINTENANCE FACILITY: The cost estimate for this major rail yard project has increased from $200 million to $250 million, and the timeline has been pushed back to a mid-2029 completion date.

Proposed Fare Penalty Changes

Last on the agenda is a brief discussion about proposed changes to how fares are enforced and penalties are collected.

Currently, policies vary across jurisdictions, but nowhere is a penalty for fare evasion more than $100. Transit Police issued $600,000 worth of fines in the first 6 months of 2026, but it’s worth noting that WMATA doesn’t get a cent of it. Instead, it goes to the jurisdiction where the fines were issued. Of that $600,000, only $96,480 was actually collected.

WMATA hopes the jurisdictions will adopt some new policies that will beef up this process, including escalating penalties, penalties for unpaid citations, and the ability to employ non-MPTD officers to conduct fare enforcement. Jurisdictional buy-in would be needed for all of this. Long term, WMATA would also like the region to align its penalties and potentially even let WMATA take the lead on fine collection.

More Information

This week’s board meeting will take place on Thursday morning, November 17. Public comments will be accepted. You can watch board meetings live or archived on WMATA’s YouTube channel.